| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Constr of Cement Concrete Roads | 2,754 | 26 | 1,999 | 155 | 22.72 | 13.93 | 61% |
| 2 | Rural Housing | 2,299 | 45 | 1,907 | 15 | 3.92 | 2.92 | 74% |
| 3 | Construction of Road and Culvert | 2,162 | 25 | 1,335 | 50 | 94.59 | 61.11 | 65% |
| 4 | Cattle Shed | 2,073 | 0 | 1,299 | 11 | 21.12 | 14.65 | 69% |
| 5 | Construction of Toilets | 1,973 | 0 | 1,251 | 6 | 0.77 | 0.53 | 69% |
| 6 | Construction of Check Dam/Stop Dam | 1,816 | 59 | 1,076 | 376 | 169.18 | 144.94 | 86% |
| 7 | Plantation | 1,510 | 152 | 781 | 305 | 34.73 | 10.29 | 30% |
| 8 | Construction of Bund | 1,440 | 229 | 332 | 197 | 110.34 | 79.38 | 72% |
| 9 | Construction of Tank | 1,066 | 279 | 85 | 103 | 74.91 | 53.80 | 72% |
| 10 | Farm Pond | 989 | 85 | 684 | 19 | 5.30 | 3.83 | 72% |
| 11 | Works for Flood Control and Protection | 786 | 89 | 394 | 102 | 58.76 | 40.79 | 69% |
| 12 | Land Development | 762 | 4 | 583 | 21 | 6.67 | 5.98 | 90% |
| 13 | Construction of NADEP/Vermi Compost Pit | 723 | 20 | 354 | 242 | 2.46 | 1.39 | 57% |
| 14 | Construction of Recharge Pits | 485 | 42 | 199 | 142 | 1.02 | 0.49 | 48% |
| 15 | Repair & maint of Pond/ Tank | 268 | 2 | 89 | 116 | 3.47 | 2.28 | 66% |
| 16 | Construction of Crematorium | 259 | 22 | 123 | 29 | 5.14 | 3.19 | 62% |
| 17 | Construction of Percolation Tank | 242 | 10 | 147 | 47 | 23.00 | 18.54 | 81% |
| 18 | Boulder Check/Gully Plug | 153 | 8 | 89 | 37 | 10.47 | 8.05 | 77% |
| 19 | Well Recharge | 140 | 51 | 37 | 13 | 0.89 | 0.60 | 68% |
| 20 | Construction of Trench | 137 | 6 | 99 | 12 | 4.82 | 3.45 | 72% |
| 21 | Community Sanitary Complex | 123 | 11 | 81 | 10 | 0.91 | 0.42 | 46% |
| 22 | Renovation of traditional water bodies | 108 | 0 | 77 | 5 | 1.58 | 1.12 | 71% |
| 23 | Solid and Liquid Waste Management | 100 | 0 | 6 | 73 | 0.03 | 0.02 | 61% |
| 24 | Construction of Play field | 83 | 1 | 62 | 8 | 2.57 | 1.53 | 60% |
| 25 | Constr of Aganwadi | 69 | 7 | 40 | 8 | 1.61 | 0.94 | 58% |
| 26 | Constr of GP Bhawan | 65 | 3 | 36 | 12 | 4.88 | 2.55 | 52% |
| 27 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 49 | 4 | 19 | 18 | 4.49 | 3.29 | 73% |
| 28 | Constr of Gabion | 45 | 1 | 8 | 24 | 1.49 | 1.38 | 93% |
| 29 | Roof Water Harvesting on gov/panchayat bldg | 36 | 0 | 14 | 19 | 0.65 | 0.55 | 85% |
| 30 | Grass Land Development | 27 | 11 | 6 | 10 | 1.56 | 0.51 | 32% |
| 31 | Construction of Embankment | 22 | 2 | 9 | 8 | 1.57 | 1.25 | 80% |
| 32 | Deepening / Desilting of Flood Channels | 21 | 0 | 13 | 0 | 0.12 | 0.14 | 118% |
| 33 | Constr of Food Grain storage | 14 | 0 | 3 | 10 | 1.10 | 0.33 | 30% |
| 34 | Construction of Canal | 13 | 0 | 11 | 1 | 1.93 | 1.43 | 74% |
| 35 | Construction of Spur | 12 | 1 | 5 | 5 | 0.95 | 0.76 | 80% |
| 36 | Terracing | 12 | 0 | 2 | 3 | 0.14 | 0.13 | 90% |
| 37 | Culvert | 11 | 0 | 3 | 1 | 0.04 | 0.04 | 81% |
| 38 | Constr of Compound wall | 10 | 3 | 4 | 2 | 0.23 | 0.11 | 48% |
| 39 | Repair & maint of Road | 9 | 0 | 4 | 1 | 0.08 | 0.02 | 26% |
| 40 | Nursery Development | 8 | 1 | 0 | 3 | 0.87 | 0.13 | 15% |
| 41 | Repaire and Maint of NADEP/Vermi Compost Pit | 7 | 2 | 1 | 3 | 0.07 | 0.01 | 10% |
| 42 | Repair & Maint of Bund | 7 | 1 | 2 | 3 | 0.40 | 0.17 | 42% |
| 43 | Bio-Fertilizer | 4 | 0 | 4 | 0 | 0.03 | 0.03 | 78% |
| 44 | Underground Dyke for Ground Water Recharge | 4 | 0 | 4 | 0 | 0.25 | 0.23 | 92% |
| 45 | Repair & maint of Water Harvesting Structures | 4 | 1 | 2 | 1 | 0.11 | 0.09 | 77% |
| 46 | Construction of building/workshed for SHG | 4 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 47 | Construction of Well | 4 | 0 | 1 | 1 | 0.03 | 0.01 | 48% |
| 48 | Repair & Maint of Community infrastructure | 4 | 1 | 2 | 0 | 0.08 | 0.08 | 93% |
| 49 | Lining of Canal | 2 | 0 | 1 | 0 | 0.01 | 0.03 | 511% |
| 50 | Repair & Maint of Check Dam/Stop Dam | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 51 | Repair & maint of Percolation Tank | 2 | 0 | 2 | 0 | 0.27 | 0.25 | 92% |
| 52 | Strengthening of Embankment | 2 | 0 | 2 | 0 | 0.05 | 0.05 | 107% |
| 53 | Other Works | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 54 | Construction of Fish Drying Infrastructure | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 55 | Construction of Other Community Building/Assets | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 56 | Renovation of Canal | 1 | 0 | 0 | 0 | 0.20 | 0.00 | 0% |
| Total | 22,924 | 1,204 | 13,287 | 2,229 | 682.58 | 487.71 |