| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 2,992 | 475 | 2,136 | 16 | 5.39 | 4.31 | 80% |
| 2 | Land Development | 2,700 | 4 | 1,588 | 145 | 13.35 | 8.08 | 61% |
| 3 | Construction of Bund | 2,507 | 15 | 1,145 | 796 | 23.31 | 13.84 | 59% |
| 4 | Cattle Shed | 2,269 | 28 | 881 | 546 | 16.67 | 9.51 | 57% |
| 5 | Constr of Cement Concrete Roads | 1,635 | 18 | 1,145 | 103 | 16.49 | 10.89 | 66% |
| 6 | Construction of Toilets | 1,541 | 0 | 859 | 111 | 1.28 | 0.45 | 35% |
| 7 | Plantation | 985 | 108 | 297 | 237 | 22.95 | 5.33 | 23% |
| 8 | Construction of Road and Culvert | 960 | 17 | 483 | 138 | 81.12 | 56.78 | 70% |
| 9 | Construction of NADEP/Vermi Compost Pit | 940 | 18 | 489 | 203 | 4.49 | 0.60 | 14% |
| 10 | Construction of Tank | 901 | 44 | 282 | 307 | 53.27 | 34.95 | 66% |
| 11 | Construction of Check Dam/Stop Dam | 823 | 25 | 382 | 196 | 51.22 | 39.01 | 76% |
| 12 | Works for Flood Control and Protection | 812 | 56 | 254 | 296 | 35.30 | 21.43 | 61% |
| 13 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 794 | 16 | 380 | 213 | 46.06 | 36.12 | 78% |
| 14 | Farm Pond | 738 | 61 | 210 | 100 | 12.84 | 7.02 | 55% |
| 15 | Construction of Trench | 580 | 8 | 263 | 122 | 13.76 | 8.46 | 62% |
| 16 | Construction of Crematorium | 309 | 9 | 174 | 54 | 8.24 | 5.38 | 65% |
| 17 | Repair & maint of Pond/ Tank | 226 | 1 | 83 | 89 | 2.72 | 1.67 | 62% |
| 18 | Solid and Liquid Waste Management | 218 | 7 | 86 | 74 | 1.18 | 0.62 | 52% |
| 19 | Construction of Percolation Tank | 210 | 4 | 87 | 46 | 8.69 | 6.52 | 75% |
| 20 | Construction of Play field | 186 | 0 | 104 | 16 | 4.42 | 2.19 | 50% |
| 21 | Construction of Canal | 135 | 1 | 46 | 45 | 3.36 | 1.87 | 56% |
| 22 | Constr of GP Bhawan | 133 | 17 | 52 | 38 | 5.55 | 2.25 | 41% |
| 23 | Terracing | 131 | 3 | 58 | 43 | 2.00 | 1.31 | 66% |
| 24 | Lining of Canal | 100 | 8 | 37 | 32 | 3.13 | 1.90 | 61% |
| 25 | Constr of Aganwadi | 82 | 8 | 60 | 3 | 2.63 | 1.80 | 69% |
| 26 | Well Recharge | 76 | 1 | 19 | 13 | 0.54 | 0.27 | 49% |
| 27 | Community Sanitary Complex | 64 | 3 | 43 | 10 | 0.41 | 0.19 | 45% |
| 28 | Construction of Recharge Pits | 61 | 3 | 22 | 17 | 1.74 | 1.23 | 71% |
| 29 | Construction of Well | 58 | 0 | 31 | 7 | 0.60 | 0.37 | 61% |
| 30 | Other Works | 42 | 0 | 8 | 30 | 0.03 | 0.03 | 90% |
| 31 | Repair & Maint of Bund | 32 | 1 | 4 | 19 | 0.14 | 0.09 | 66% |
| 32 | Roof Water Harvesting on gov/panchayat bldg | 32 | 0 | 17 | 6 | 0.79 | 0.52 | 66% |
| 33 | Repair & maint of Water Harvesting Structures | 23 | 0 | 6 | 9 | 0.70 | 0.63 | 90% |
| 34 | Lift Irrigation | 21 | 0 | 19 | 0 | 1.02 | 0.70 | 69% |
| 35 | Culvert | 17 | 1 | 6 | 4 | 0.85 | 0.55 | 65% |
| 36 | Repair & Maint of Community infrastructure | 16 | 1 | 8 | 0 | 0.27 | 0.20 | 75% |
| 37 | Nursery Development | 16 | 0 | 0 | 0 | 0.20 | 0.00 | 0% |
| 38 | Renovation of traditional water bodies | 15 | 0 | 12 | 0 | 0.20 | 0.07 | 37% |
| 39 | Repair & Maint of Check Dam/Stop Dam | 14 | 1 | 2 | 2 | 0.37 | 0.20 | 55% |
| 40 | Constr of Compound wall | 14 | 8 | 2 | 2 | 1.39 | 0.20 | 14% |
| 41 | Construction of Other Community Building/Assets | 13 | 0 | 0 | 1 | 0.02 | 0.00 | 0% |
| 42 | Constr of Gabion | 13 | 0 | 9 | 3 | 1.14 | 0.85 | 75% |
| 43 | Repair & maint of Road | 10 | 2 | 3 | 0 | 1.18 | 0.72 | 61% |
| 44 | Boulder Check/Gully Plug | 10 | 1 | 4 | 2 | 0.25 | 0.20 | 79% |
| 45 | Construction of Embankment | 9 | 0 | 2 | 4 | 0.35 | 0.15 | 44% |
| 46 | Constr of Food Grain storage | 9 | 0 | 3 | 1 | 0.36 | 0.26 | 73% |
| 47 | Construction of Spur | 8 | 1 | 4 | 0 | 0.42 | 0.31 | 75% |
| 48 | Repair & maint of Percolation Tank | 6 | 0 | 3 | 2 | 0.18 | 0.17 | 91% |
| 49 | Constr of Kitchen Shed | 6 | 1 | 1 | 1 | 0.28 | 0.09 | 34% |
| 50 | Goat Shelter | 5 | 0 | 4 | 1 | 0.02 | 0.03 | 114% |
| 51 | Construction of building/workshed for SHG | 5 | 0 | 3 | 0 | 0.36 | 0.30 | 85% |
| 52 | Deepening / Desilting of Flood Channels | 4 | 0 | 2 | 1 | 0.53 | 0.28 | 52% |
| 53 | Renovation of Canal | 4 | 0 | 1 | 1 | 0.02 | 0.02 | 98% |
| 54 | Bio-gas plant | 3 | 0 | 0 | 0 | 0.02 | 0.00 | 0% |
| 55 | Poultry Shelter | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 56 | Bio-Fertilizer | 2 | 0 | 1 | 1 | 0.01 | 0.01 | 59% |
| 57 | Underground Dyke for Ground Water Recharge | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 58 | Grass Land Development | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 59 | Construction of Fish Drying Infrastructure | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 60 | Piggery Shelter | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 61 | Construction of Village Haats | 1 | 0 | 0 | 0 | 0.08 | 0.00 | 0% |
| Total | 23,524 | 975 | 11,820 | 4,109 | 453.90 | 290.95 |