| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 4,866 | 1,015 | 2,523 | 185 | 9.38 | 6.10 | 65% |
| 2 | Constr of Cement Concrete Roads | 3,369 | 159 | 2,061 | 468 | 48.30 | 13.97 | 29% |
| 3 | Land Development | 2,167 | 5 | 811 | 822 | 10.08 | 6.56 | 65% |
| 4 | Construction of Bund | 1,786 | 50 | 1,045 | 401 | 18.41 | 9.14 | 50% |
| 5 | Cattle Shed | 1,604 | 108 | 432 | 798 | 12.62 | 7.22 | 57% |
| 6 | Construction of NADEP/Vermi Compost Pit | 1,453 | 41 | 829 | 438 | 1.27 | 0.87 | 69% |
| 7 | Solid and Liquid Waste Management | 1,308 | 7 | 950 | 152 | 1.36 | 0.66 | 49% |
| 8 | Farm Pond | 837 | 73 | 287 | 280 | 10.79 | 4.09 | 38% |
| 9 | Construction of Road and Culvert | 789 | 25 | 380 | 112 | 39.90 | 23.74 | 60% |
| 10 | Plantation | 749 | 79 | 190 | 294 | 14.81 | 2.74 | 19% |
| 11 | Construction of Toilets | 733 | 8 | 593 | 4 | 0.50 | 0.34 | 67% |
| 12 | Construction of Check Dam/Stop Dam | 541 | 19 | 242 | 188 | 22.96 | 17.46 | 76% |
| 13 | Works for Flood Control and Protection | 416 | 75 | 137 | 145 | 14.10 | 5.86 | 42% |
| 14 | Construction of Trench | 203 | 2 | 46 | 84 | 3.98 | 2.02 | 51% |
| 15 | Construction of Crematorium | 185 | 11 | 80 | 46 | 3.05 | 1.64 | 54% |
| 16 | Repair & maint of Pond/ Tank | 118 | 9 | 35 | 63 | 1.62 | 0.85 | 53% |
| 17 | Renovation of traditional water bodies | 118 | 0 | 94 | 5 | 2.18 | 1.19 | 55% |
| 18 | Construction of Embankment | 116 | 23 | 33 | 54 | 10.73 | 4.04 | 38% |
| 19 | Construction of Tank | 107 | 12 | 24 | 53 | 7.90 | 3.46 | 44% |
| 20 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 100 | 9 | 32 | 20 | 2.00 | 0.77 | 39% |
| 21 | Constr of Aganwadi | 95 | 13 | 54 | 20 | 3.45 | 2.28 | 66% |
| 22 | Construction of Play field | 82 | 6 | 20 | 41 | 0.99 | 0.31 | 31% |
| 23 | Construction of Percolation Tank | 71 | 3 | 15 | 22 | 2.05 | 0.94 | 46% |
| 24 | Piggery Shelter | 69 | 0 | 0 | 46 | 0.00 | 0.00 | 0% |
| 25 | Constr of Food Grain storage | 60 | 2 | 2 | 56 | 0.73 | 0.07 | 9% |
| 26 | Well Recharge | 48 | 2 | 15 | 11 | 0.10 | 0.05 | 46% |
| 27 | Other Works | 45 | 1 | 19 | 22 | 0.25 | 0.19 | 77% |
| 28 | Terracing | 44 | 2 | 20 | 17 | 0.86 | 0.31 | 36% |
| 29 | Constr of GP Bhawan | 44 | 13 | 15 | 10 | 2.86 | 1.03 | 36% |
| 30 | Repair & Maint of Bund | 36 | 0 | 8 | 27 | 0.32 | 0.15 | 46% |
| 31 | Community Sanitary Complex | 30 | 6 | 18 | 6 | 0.12 | 0.09 | 72% |
| 32 | Construction of Well | 29 | 0 | 26 | 0 | 0.12 | 0.21 | 179% |
| 33 | Repair & maint of Road | 25 | 3 | 12 | 7 | 0.65 | 0.35 | 54% |
| 34 | Construction of Recharge Pits | 17 | 0 | 1 | 6 | 0.04 | 0.02 | 43% |
| 35 | Repair & Maint of Check Dam/Stop Dam | 16 | 0 | 2 | 10 | 1.13 | 0.79 | 70% |
| 36 | Constr of Compound wall | 16 | 4 | 5 | 1 | 0.70 | 0.45 | 64% |
| 37 | Boulder Check/Gully Plug | 15 | 0 | 12 | 2 | 0.07 | 0.03 | 51% |
| 38 | Construction of Other Community Building/Assets | 15 | 0 | 2 | 3 | 0.11 | 0.11 | 102% |
| 39 | Grass Land Development | 14 | 3 | 0 | 9 | 1.41 | 0.39 | 28% |
| 40 | Constr of Kitchen Shed | 13 | 4 | 6 | 3 | 0.40 | 0.31 | 78% |
| 41 | Culvert | 11 | 0 | 3 | 1 | 0.12 | 0.06 | 48% |
| 42 | Repair & Maint of Community infrastructure | 9 | 0 | 1 | 2 | 0.04 | 0.00 | 11% |
| 43 | Construction of building/workshed for SHG | 9 | 0 | 0 | 0 | 0.03 | 0.00 | 0% |
| 44 | Constr of Gabion | 8 | 0 | 1 | 5 | 0.01 | 0.00 | 25% |
| 45 | Deepening / Desilting of Flood Channels | 6 | 0 | 0 | 5 | 0.00 | 0.00 | 0% |
| 46 | Repair & maint of Water Harvesting Structures | 6 | 1 | 0 | 5 | 0.07 | 0.00 | 1% |
| 47 | Nursery Development | 6 | 0 | 2 | 0 | 0.08 | 0.00 | 3% |
| 48 | Underground Dyke for Ground Water Recharge | 3 | 0 | 1 | 0 | 0.00 | 0.00 | 73% |
| 49 | Repair & maint of Percolation Tank | 3 | 0 | 0 | 3 | 0.00 | 0.00 | 0% |
| 50 | Goat Shelter | 3 | 0 | 2 | 0 | 0.39 | 0.01 | 3% |
| 51 | Construction of Spur | 2 | 0 | 0 | 2 | 0.01 | 0.00 | 0% |
| 52 | Roof Water Harvesting on gov/panchayat bldg | 2 | 1 | 0 | 1 | 0.15 | 0.00 | 2% |
| 53 | Lining of Canal | 1 | 0 | 0 | 0 | 0.03 | 0.00 | 0% |
| 54 | Repaire and Maint of NADEP/Vermi Compost Pit | 1 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 55 | Bio-Fertilizer | 1 | 0 | 1 | 0 | 0.00 | 0.00 | 78% |
| 56 | Construction of Canal | 1 | 0 | 1 | 0 | 0.04 | 0.04 | 100% |
| Total | 22,421 | 1,794 | 11,088 | 4,956 | 253.26 | 120.92 |