| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 25,829 | 4,451 | 15,337 | 389 | 53.87 | 35.67 | 66% |
| 2 | Land Development | 12,226 | 28 | 5,647 | 2,999 | 85.66 | 44.26 | 52% |
| 3 | Farm Pond | 6,182 | 24 | 4,747 | 218 | 34.05 | 17.63 | 52% |
| 4 | Construction of Check Dam/Stop Dam | 4,593 | 38 | 1,618 | 900 | 116.05 | 42.84 | 37% |
| 5 | Construction of Bund | 3,605 | 19 | 1,333 | 1,590 | 34.54 | 23.20 | 67% |
| 6 | Constr of Cement Concrete Roads | 3,156 | 143 | 1,647 | 722 | 59.03 | 37.46 | 64% |
| 7 | Renovation of traditional water bodies | 2,543 | 0 | 1,420 | 7 | 23.31 | 19.47 | 84% |
| 8 | Cattle Shed | 2,479 | 49 | 639 | 1,346 | 13.75 | 8.14 | 59% |
| 9 | Construction of Road and Culvert | 2,233 | 33 | 1,163 | 382 | 61.24 | 46.38 | 76% |
| 10 | Plantation | 2,210 | 172 | 742 | 694 | 37.73 | 12.64 | 34% |
| 11 | Construction of NADEP/Vermi Compost Pit | 1,039 | 32 | 480 | 412 | 3.21 | 1.96 | 61% |
| 12 | Construction of Tank | 663 | 23 | 160 | 255 | 17.42 | 10.55 | 61% |
| 13 | Construction of Trench | 622 | 8 | 351 | 151 | 24.37 | 8.58 | 35% |
| 14 | Solid and Liquid Waste Management | 478 | 38 | 197 | 176 | 5.52 | 3.76 | 68% |
| 15 | Construction of Toilets | 471 | 9 | 327 | 29 | 1.61 | 1.32 | 82% |
| 16 | Construction of Well | 410 | 10 | 178 | 102 | 5.28 | 3.34 | 63% |
| 17 | Well Recharge | 359 | 9 | 82 | 110 | 5.37 | 2.67 | 50% |
| 18 | Repair & maint of Pond/ Tank | 358 | 6 | 123 | 150 | 7.34 | 4.12 | 56% |
| 19 | Constr of GP Bhawan | 353 | 23 | 175 | 108 | 6.74 | 3.70 | 55% |
| 20 | Terracing | 352 | 8 | 129 | 170 | 4.05 | 2.63 | 65% |
| 21 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 292 | 5 | 105 | 133 | 5.60 | 3.36 | 60% |
| 22 | Boulder Check/Gully Plug | 286 | 1 | 118 | 150 | 2.43 | 1.78 | 73% |
| 23 | Culvert | 262 | 31 | 138 | 37 | 5.89 | 4.67 | 79% |
| 24 | Constr of Aganwadi | 231 | 12 | 114 | 49 | 4.44 | 2.28 | 51% |
| 25 | Construction of Crematorium | 210 | 4 | 130 | 6 | 4.64 | 1.68 | 36% |
| 26 | Goat Shelter | 206 | 1 | 15 | 155 | 0.67 | 0.48 | 71% |
| 27 | Construction of Recharge Pits | 174 | 5 | 44 | 60 | 1.00 | 0.59 | 60% |
| 28 | Construction of Percolation Tank | 166 | 2 | 35 | 45 | 2.58 | 1.71 | 66% |
| 29 | Repair & maint of Road | 159 | 6 | 68 | 46 | 2.70 | 1.80 | 67% |
| 30 | Other Works | 144 | 3 | 28 | 92 | 1.01 | 0.32 | 31% |
| 31 | Constr of Compound wall | 123 | 10 | 54 | 41 | 2.82 | 1.96 | 70% |
| 32 | Constr of Food Grain storage | 122 | 10 | 33 | 54 | 1.45 | 0.74 | 51% |
| 33 | Roof Water Harvesting on gov/panchayat bldg | 120 | 3 | 12 | 27 | 1.02 | 0.51 | 50% |
| 34 | Repair & Maint of Community infrastructure | 120 | 4 | 58 | 40 | 1.73 | 0.85 | 49% |
| 35 | Repair & Maint of Check Dam/Stop Dam | 115 | 4 | 48 | 51 | 1.23 | 0.86 | 70% |
| 36 | Construction of Play field | 106 | 6 | 44 | 33 | 2.55 | 1.53 | 60% |
| 37 | Repair & maint of Water Harvesting Structures | 82 | 4 | 28 | 40 | 1.50 | 0.81 | 54% |
| 38 | Poultry Shelter | 78 | 0 | 15 | 47 | 0.24 | 0.09 | 36% |
| 39 | Construction of Other Community Building/Assets | 69 | 1 | 16 | 26 | 0.91 | 0.78 | 85% |
| 40 | Constr of Gabion | 63 | 0 | 22 | 36 | 1.25 | 0.75 | 60% |
| 41 | Construction of building/workshed for SHG | 63 | 6 | 15 | 20 | 1.68 | 1.14 | 68% |
| 42 | Piggery Shelter | 61 | 0 | 7 | 43 | 0.10 | 0.04 | 37% |
| 43 | Community Sanitary Complex | 59 | 10 | 24 | 20 | 0.52 | 0.16 | 31% |
| 44 | Repair & Maint of Bund | 58 | 1 | 13 | 35 | 0.69 | 0.47 | 69% |
| 45 | Construction of Fish Drying Infrastructure | 47 | 0 | 7 | 14 | 0.17 | 0.09 | 53% |
| 46 | Construction of Spur | 42 | 1 | 17 | 15 | 1.35 | 0.89 | 66% |
| 47 | Bio-Fertilizer | 40 | 0 | 6 | 18 | 0.14 | 0.02 | 17% |
| 48 | Works for Flood Control and Protection | 28 | 1 | 5 | 12 | 0.27 | 0.22 | 82% |
| 49 | Construction of Village Haats | 26 | 2 | 11 | 8 | 0.24 | 0.12 | 49% |
| 50 | Constr of Kitchen Shed | 26 | 0 | 9 | 15 | 0.16 | 0.09 | 59% |
| 51 | Underground Dyke for Ground Water Recharge | 23 | 0 | 11 | 2 | 0.24 | 0.22 | 91% |
| 52 | Construction of Canal | 23 | 2 | 5 | 7 | 0.59 | 0.13 | 22% |
| 53 | Construction of Embankment | 22 | 0 | 7 | 11 | 0.55 | 0.46 | 83% |
| 54 | Repaire and Maint of NADEP/Vermi Compost Pit | 21 | 0 | 10 | 10 | 0.57 | 0.51 | 91% |
| 55 | Grass Land Development | 19 | 1 | 4 | 13 | 0.16 | 0.08 | 52% |
| 56 | Repair & maint of Percolation Tank | 19 | 0 | 4 | 12 | 0.19 | 0.14 | 75% |
| 57 | Nursery Development | 19 | 1 | 4 | 8 | 0.35 | 0.08 | 22% |
| 58 | Lining of Canal | 11 | 0 | 1 | 6 | 0.12 | 0.02 | 19% |
| 59 | Bio-gas plant | 9 | 1 | 0 | 0 | 0.11 | 0.00 | 0% |
| 60 | Deepening / Desilting of Flood Channels | 6 | 0 | 1 | 3 | 0.03 | 0.01 | 20% |
| 61 | Renovation of Canal | 3 | 0 | 0 | 2 | 0.11 | 0.00 | 0% |
| 62 | Repair & Maint of Canal | 2 | 0 | 0 | 1 | 0.28 | 0.00 | 0% |
| Total | 73,916 | 5,261 | 37,781 | 12,353 | 654.38 | 362.74 |