| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 11,456 | 2,388 | 6,907 | 60 | 23.20 | 18.46 | 80% |
| 2 | Construction of Check Dam/Stop Dam | 3,709 | 13 | 2,228 | 718 | 93.49 | 59.08 | 63% |
| 3 | Construction of Toilets | 3,650 | 1 | 3,120 | 160 | 4.26 | 3.27 | 77% |
| 4 | Construction of NADEP/Vermi Compost Pit | 3,088 | 13 | 2,218 | 550 | 4.06 | 2.47 | 61% |
| 5 | Plantation | 2,577 | 279 | 1,202 | 427 | 56.27 | 23.75 | 42% |
| 6 | Construction of Well | 2,379 | 65 | 1,540 | 180 | 26.35 | 19.39 | 74% |
| 7 | Land Development | 2,275 | 4 | 1,260 | 268 | 8.01 | 4.94 | 62% |
| 8 | Construction of Trench | 1,603 | 1 | 782 | 330 | 40.52 | 22.61 | 56% |
| 9 | Construction of Bund | 1,363 | 0 | 899 | 358 | 19.11 | 13.35 | 70% |
| 10 | Well Recharge | 1,362 | 4 | 443 | 245 | 9.02 | 5.75 | 64% |
| 11 | Construction of Recharge Pits | 1,310 | 2 | 296 | 452 | 2.42 | 1.26 | 52% |
| 12 | Constr of Cement Concrete Roads | 1,234 | 8 | 791 | 178 | 14.66 | 8.76 | 60% |
| 13 | Construction of Road and Culvert | 1,093 | 13 | 571 | 145 | 62.64 | 31.22 | 50% |
| 14 | Cattle Shed | 749 | 10 | 398 | 100 | 4.14 | 2.76 | 67% |
| 15 | Construction of Tank | 690 | 57 | 275 | 195 | 30.84 | 18.58 | 60% |
| 16 | Farm Pond | 640 | 0 | 268 | 30 | 7.93 | 4.56 | 58% |
| 17 | Boulder Check/Gully Plug | 566 | 1 | 278 | 266 | 1.78 | 1.27 | 71% |
| 18 | Terracing | 298 | 3 | 168 | 105 | 6.51 | 4.52 | 69% |
| 19 | Construction of Percolation Tank | 265 | 2 | 123 | 49 | 5.77 | 2.83 | 49% |
| 20 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 243 | 1 | 164 | 49 | 6.25 | 4.76 | 76% |
| 21 | Solid and Liquid Waste Management | 211 | 4 | 95 | 77 | 1.39 | 0.81 | 58% |
| 22 | Repair & Maint of Check Dam/Stop Dam | 192 | 1 | 86 | 72 | 4.53 | 3.49 | 77% |
| 23 | Repair & maint of Percolation Tank | 159 | 0 | 37 | 114 | 0.65 | 0.47 | 72% |
| 24 | Goat Shelter | 157 | 4 | 86 | 37 | 0.57 | 0.39 | 68% |
| 25 | Underground Dyke for Ground Water Recharge | 153 | 0 | 60 | 70 | 1.00 | 0.48 | 48% |
| 26 | Repair & maint of Pond/ Tank | 127 | 2 | 38 | 54 | 2.72 | 1.32 | 48% |
| 27 | Constr of Gabion | 124 | 0 | 44 | 78 | 0.56 | 0.32 | 58% |
| 28 | Repair & maint of Water Harvesting Structures | 117 | 2 | 63 | 40 | 2.88 | 2.21 | 77% |
| 29 | Constr of Aganwadi | 100 | 3 | 65 | 22 | 1.61 | 1.19 | 74% |
| 30 | Roof Water Harvesting on gov/panchayat bldg | 80 | 1 | 27 | 38 | 1.52 | 1.12 | 74% |
| 31 | Construction of Crematorium | 75 | 0 | 60 | 1 | 1.57 | 1.10 | 70% |
| 32 | Community Sanitary Complex | 70 | 5 | 31 | 24 | 0.79 | 0.15 | 19% |
| 33 | Repair & maint of Road | 62 | 0 | 34 | 22 | 2.01 | 1.41 | 70% |
| 34 | Other Works | 53 | 1 | 20 | 23 | 1.02 | 0.57 | 56% |
| 35 | Repair & Maint of Bund | 46 | 0 | 22 | 18 | 0.78 | 0.48 | 61% |
| 36 | Works for Flood Control and Protection | 33 | 1 | 20 | 3 | 1.81 | 1.12 | 62% |
| 37 | Construction of Embankment | 30 | 0 | 20 | 8 | 1.70 | 1.26 | 74% |
| 38 | Construction of Spur | 30 | 1 | 13 | 14 | 0.71 | 0.54 | 77% |
| 39 | Construction of Play field | 28 | 0 | 15 | 2 | 0.48 | 0.20 | 42% |
| 40 | Constr of Compound wall | 27 | 17 | 1 | 1 | 0.44 | 0.19 | 42% |
| 41 | Constr of GP Bhawan | 24 | 1 | 11 | 8 | 0.60 | 0.49 | 82% |
| 42 | Nursery Development | 24 | 0 | 7 | 2 | 0.73 | 0.13 | 18% |
| 43 | Culvert | 21 | 0 | 7 | 8 | 1.52 | 0.82 | 54% |
| 44 | Constr of Food Grain storage | 21 | 0 | 11 | 7 | 0.86 | 0.80 | 93% |
| 45 | Constr of Kitchen Shed | 18 | 0 | 8 | 9 | 0.03 | 0.01 | 32% |
| 46 | Repaire and Maint of NADEP/Vermi Compost Pit | 18 | 0 | 7 | 9 | 0.02 | 0.01 | 51% |
| 47 | Renovation of traditional water bodies | 10 | 0 | 6 | 3 | 0.06 | 0.05 | 88% |
| 48 | Construction of Fish Drying Infrastructure | 9 | 0 | 1 | 2 | 0.03 | 0.01 | 45% |
| 49 | Construction of building/workshed for SHG | 8 | 1 | 1 | 4 | 0.22 | 0.13 | 62% |
| 50 | Poultry Shelter | 8 | 0 | 3 | 4 | 0.03 | 0.01 | 32% |
| 51 | Repair & Maint of Community infrastructure | 6 | 1 | 1 | 4 | 0.13 | 0.05 | 39% |
| 52 | Grass Land Development | 5 | 0 | 4 | 0 | 0.12 | 0.05 | 42% |
| 53 | Bio-gas plant | 5 | 0 | 2 | 0 | 0.01 | 0.01 | 91% |
| 54 | Construction of Canal | 4 | 0 | 2 | 0 | 0.44 | 0.06 | 13% |
| 55 | Piggery Shelter | 4 | 0 | 1 | 1 | 0.04 | 0.00 | 0% |
| 56 | Lining of Canal | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 57 | Renovation of Canal | 2 | 0 | 1 | 0 | 0.06 | 0.00 | 4% |
| 58 | Bio-Fertilizer | 2 | 0 | 0 | 1 | 0.00 | 0.00 | 0% |
| 59 | Deepening / Desilting of Flood Channels | 1 | 0 | 0 | 0 | 0.01 | 0.00 | 0% |
| 60 | Construction of Other Community Building/Assets | 1 | 0 | 0 | 0 | 0.10 | 0.00 | 0% |
| 61 | Construction of Village Haats | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 42,618 | 2,910 | 24,841 | 5,646 | 460.99 | 275.05 |