| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Plantation | 329 | 202 | 0 | 0 | 6.19 | 0.03 | 1% |
| 2 | Rural Housing | 300 | 156 | 2 | 0 | 0.87 | 0.01 | 1% |
| 3 | Construction of Check Dam/Stop Dam | 191 | 6 | 0 | 0 | 1.20 | 0.00 | 0% |
| 4 | Farm Pond | 122 | 14 | 0 | 0 | 1.21 | 0.00 | 0% |
| 5 | Construction of Trench | 113 | 30 | 0 | 0 | 1.31 | 0.06 | 5% |
| 6 | Well Recharge | 79 | 1 | 0 | 0 | 0.11 | 0.00 | 0% |
| 7 | Construction of Tank | 58 | 8 | 0 | 0 | 2.58 | 0.01 | 0% |
| 8 | Land Development | 56 | 17 | 1 | 0 | 0.92 | 0.00 | 0% |
| 9 | Construction of Well | 47 | 18 | 0 | 0 | 0.64 | 0.00 | 0% |
| 10 | Repair & maint of Pond/ Tank | 34 | 4 | 0 | 0 | 0.39 | 0.00 | 0% |
| 11 | Construction of Recharge Pits | 34 | 0 | 0 | 0 | 0.05 | 0.00 | 0% |
| 12 | Roof Water Harvesting on gov/panchayat bldg | 28 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 13 | Construction of Percolation Tank | 26 | 2 | 0 | 0 | 0.07 | 0.00 | 0% |
| 14 | Construction of Road and Culvert | 15 | 8 | 0 | 0 | 1.70 | 0.00 | 0% |
| 15 | Underground Dyke for Ground Water Recharge | 11 | 2 | 0 | 0 | 0.23 | 0.00 | 0% |
| 16 | Constr of Cement Concrete Roads | 5 | 0 | 0 | 0 | 0.01 | 0.00 | 0% |
| 17 | Repair & Maint of Community infrastructure | 4 | 2 | 0 | 0 | 0.03 | 0.00 | 0% |
| 18 | Repair & Maint of Check Dam/Stop Dam | 4 | 2 | 0 | 0 | 0.14 | 0.00 | 0% |
| 19 | Other Works | 3 | 2 | 0 | 0 | 0.04 | 0.00 | 0% |
| 20 | Community Sanitary Complex | 3 | 2 | 0 | 0 | 0.01 | 0.00 | 0% |
| 21 | Construction of Bund | 3 | 3 | 0 | 0 | 0.04 | 0.00 | 0% |
| 22 | Constr of Gabion | 3 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 23 | Bio-gas plant | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 24 | Boulder Check/Gully Plug | 2 | 2 | 0 | 0 | 0.05 | 0.00 | 0% |
| 25 | Cattle Shed | 2 | 2 | 0 | 0 | 0.02 | 0.00 | 0% |
| 26 | Constr of Compound wall | 2 | 1 | 0 | 0 | 0.02 | 0.00 | 0% |
| 27 | Construction of Crematorium | 2 | 0 | 0 | 0 | 0.02 | 0.00 | 0% |
| 28 | Construction of Play field | 2 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 29 | Nursery Development | 2 | 2 | 0 | 0 | 0.78 | 0.00 | 0% |
| 30 | Terracing | 2 | 1 | 0 | 0 | 0.15 | 0.00 | 0% |
| 31 | Culvert | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 32 | Solid and Liquid Waste Management | 1 | 1 | 0 | 0 | 0.00 | 0.00 | 0% |
| 33 | Works for Flood Control and Protection | 1 | 1 | 0 | 0 | 0.08 | 0.00 | 0% |
| 34 | Construction of NADEP/Vermi Compost Pit | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 35 | Constr of Food Grain storage | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| 36 | Lining of Canal | 1 | 1 | 0 | 0 | 0.08 | 0.00 | 0% |
| Total | 1,490 | 490 | 3 | 0 | 18.94 | 0.11 |