| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 17,180 | 841 | 15,444 | 112 | 32.95 | 29.86 | 91% |
| 2 | Construction of Toilets | 8,895 | 0 | 6,969 | 799 | 8.53 | 6.63 | 78% |
| 3 | Construction of Bund | 6,962 | 0 | 5,244 | 787 | 42.68 | 33.66 | 79% |
| 4 | Land Development | 5,005 | 1 | 3,783 | 323 | 43.17 | 28.67 | 66% |
| 5 | Farm Pond | 3,710 | 0 | 2,545 | 213 | 43.14 | 33.07 | 77% |
| 6 | Construction of Check Dam/Stop Dam | 3,466 | 1 | 2,088 | 210 | 45.20 | 43.39 | 96% |
| 7 | Plantation | 2,887 | 176 | 1,535 | 698 | 39.75 | 26.86 | 68% |
| 8 | Construction of Road and Culvert | 2,830 | 2 | 1,561 | 234 | 72.25 | 74.80 | 104% |
| 9 | Constr of Cement Concrete Roads | 2,272 | 4 | 1,578 | 274 | 28.74 | 19.10 | 66% |
| 10 | Solid and Liquid Waste Management | 1,438 | 5 | 597 | 617 | 3.21 | 1.75 | 54% |
| 11 | Construction of NADEP/Vermi Compost Pit | 1,090 | 0 | 516 | 410 | 3.79 | 1.81 | 48% |
| 12 | Construction of Trench | 878 | 0 | 519 | 62 | 13.04 | 11.41 | 88% |
| 13 | Construction of Tank | 388 | 0 | 125 | 82 | 10.58 | 7.64 | 72% |
| 14 | Construction of Percolation Tank | 382 | 0 | 215 | 89 | 11.64 | 8.79 | 76% |
| 15 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 349 | 1 | 240 | 51 | 6.51 | 5.22 | 80% |
| 16 | Cattle Shed | 323 | 1 | 214 | 35 | 1.96 | 1.64 | 83% |
| 17 | Repair & maint of Pond/ Tank | 301 | 1 | 155 | 80 | 13.29 | 10.30 | 78% |
| 18 | Well Recharge | 297 | 0 | 104 | 22 | 2.90 | 2.31 | 80% |
| 19 | Goat Shelter | 294 | 1 | 174 | 22 | 1.89 | 1.19 | 63% |
| 20 | Construction of Well | 272 | 2 | 171 | 36 | 4.56 | 2.88 | 63% |
| 21 | Other Works | 245 | 0 | 176 | 35 | 1.22 | 0.94 | 77% |
| 22 | Repair & maint of Road | 217 | 0 | 117 | 79 | 4.85 | 4.23 | 87% |
| 23 | Construction of Canal | 216 | 1 | 145 | 39 | 9.81 | 6.65 | 68% |
| 24 | Works for Flood Control and Protection | 198 | 0 | 99 | 50 | 10.75 | 8.78 | 82% |
| 25 | Construction of Fish Drying Infrastructure | 188 | 0 | 97 | 43 | 5.41 | 3.72 | 69% |
| 26 | Terracing | 172 | 0 | 126 | 36 | 2.50 | 1.89 | 76% |
| 27 | Constr of Aganwadi | 111 | 0 | 67 | 16 | 4.12 | 2.03 | 49% |
| 28 | Renovation of Canal | 84 | 0 | 55 | 15 | 1.98 | 1.44 | 73% |
| 29 | Repair & maint of Water Harvesting Structures | 83 | 0 | 42 | 36 | 2.49 | 1.51 | 61% |
| 30 | Construction of Recharge Pits | 76 | 0 | 13 | 15 | 0.72 | 0.43 | 60% |
| 31 | Repaire and Maint of NADEP/Vermi Compost Pit | 73 | 0 | 12 | 44 | 0.09 | 0.03 | 28% |
| 32 | Community Sanitary Complex | 69 | 3 | 50 | 14 | 0.56 | 0.29 | 51% |
| 33 | Boulder Check/Gully Plug | 66 | 0 | 49 | 10 | 1.45 | 1.14 | 79% |
| 34 | Repair & Maint of Check Dam/Stop Dam | 62 | 0 | 42 | 14 | 4.17 | 2.84 | 68% |
| 35 | Repair & Maint of Canal | 61 | 0 | 41 | 14 | 1.18 | 0.95 | 81% |
| 36 | Lining of Canal | 60 | 0 | 23 | 16 | 1.16 | 0.79 | 68% |
| 37 | Constr of Food Grain storage | 56 | 4 | 31 | 8 | 4.51 | 3.89 | 86% |
| 38 | Construction of Play field | 53 | 0 | 38 | 3 | 2.24 | 1.63 | 73% |
| 39 | Fish Culture | 49 | 0 | 18 | 10 | 1.36 | 0.73 | 53% |
| 40 | Constr of GP Bhawan | 48 | 2 | 21 | 7 | 3.15 | 1.54 | 49% |
| 41 | Deepening / Desilting of Flood Channels | 42 | 0 | 29 | 3 | 0.34 | 0.61 | 179% |
| 42 | Roof Water Harvesting on gov/panchayat bldg | 42 | 0 | 17 | 7 | 0.51 | 0.42 | 82% |
| 43 | Repair & maint of Percolation Tank | 41 | 1 | 13 | 21 | 1.30 | 0.76 | 59% |
| 44 | Renovation of traditional water bodies | 38 | 0 | 7 | 0 | 0.75 | 0.60 | 80% |
| 45 | Poultry Shelter | 37 | 0 | 27 | 4 | 0.38 | 0.19 | 49% |
| 46 | Bio-Fertilizer | 36 | 0 | 13 | 1 | 0.09 | 0.05 | 55% |
| 47 | Culvert | 33 | 0 | 16 | 0 | 0.68 | 0.43 | 63% |
| 48 | Constr of Gabion | 32 | 0 | 22 | 7 | 0.85 | 0.58 | 68% |
| 49 | Nursery Development | 30 | 0 | 13 | 12 | 0.75 | 0.43 | 57% |
| 50 | Repair & Maint of Bund | 25 | 0 | 11 | 12 | 0.92 | 0.50 | 55% |
| 51 | Strengthening of Embankment | 25 | 0 | 22 | 0 | 2.58 | 2.31 | 90% |
| 52 | Constr of Kitchen Shed | 24 | 0 | 9 | 14 | 0.04 | 0.02 | 40% |
| 53 | Constr of Compound wall | 24 | 0 | 18 | 3 | 0.38 | 0.33 | 88% |
| 54 | Construction of Crematorium | 22 | 0 | 19 | 1 | 1.24 | 1.00 | 81% |
| 55 | Repair & Maint of Fish Drying Infrastructure | 21 | 0 | 12 | 8 | 0.66 | 0.42 | 64% |
| 56 | Repair & Maint of Community infrastructure | 18 | 0 | 13 | 4 | 0.75 | 0.63 | 83% |
| 57 | Construction of Spur | 16 | 1 | 10 | 5 | 0.74 | 0.53 | 72% |
| 58 | Construction of building/workshed for SHG | 12 | 0 | 7 | 4 | 0.42 | 0.35 | 83% |
| 59 | Underground Dyke for Ground Water Recharge | 11 | 0 | 5 | 0 | 0.27 | 0.17 | 64% |
| 60 | Grass Land Development | 10 | 0 | 6 | 4 | 0.23 | 0.19 | 83% |
| 61 | Construction of Other Community Building/Assets | 8 | 0 | 2 | 2 | 0.03 | 0.02 | 49% |
| 62 | Construction of Village Haats | 4 | 0 | 0 | 1 | 0.02 | 0.00 | 0% |
| 63 | Lift Irrigation | 4 | 0 | 2 | 1 | 0.16 | 0.15 | 92% |
| 64 | Piggery Shelter | 3 | 0 | 2 | 1 | 0.01 | 0.01 | 99% |
| 65 | Construction of Embankment | 3 | 0 | 1 | 0 | 0.03 | 0.02 | 68% |
| 66 | Bio-gas plant | 1 | 0 | 0 | 0 | 0.00 | 0.00 | 0% |
| Total | 61,968 | 1,048 | 45,335 | 5,775 | 507.63 | 407.14 |