| Sr. | New Work Type | Total works | Ongoing | Completed | Closed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|---|---|---|
| 1 | Rural Housing | 17,439 | 2,100 | 13,461 | 32 | 33.99 | 26.71 | 79% |
| 2 | Constr of Cement Concrete Roads | 3,771 | 143 | 2,807 | 379 | 40.54 | 21.83 | 54% |
| 3 | Farm Pond | 2,668 | 6 | 1,775 | 128 | 28.42 | 17.83 | 63% |
| 4 | Plantation | 2,656 | 337 | 1,370 | 365 | 47.72 | 17.81 | 37% |
| 5 | Construction of Toilets | 2,480 | 0 | 1,880 | 433 | 1.70 | 1.09 | 64% |
| 6 | Construction of Well | 2,098 | 174 | 1,414 | 197 | 50.54 | 37.31 | 74% |
| 7 | Construction of Recharge Pits | 1,402 | 0 | 393 | 947 | 1.82 | 0.67 | 37% |
| 8 | Construction of Percolation Tank | 1,280 | 10 | 578 | 369 | 36.45 | 23.96 | 66% |
| 9 | Works for Flood Control and Protection | 1,087 | 38 | 752 | 225 | 55.48 | 42.84 | 77% |
| 10 | Construction of NADEP/Vermi Compost Pit | 1,023 | 1 | 391 | 539 | 1.66 | 0.84 | 51% |
| 11 | Well Recharge | 974 | 0 | 494 | 45 | 2.54 | 1.94 | 76% |
| 12 | Construction of Road and Culvert | 680 | 47 | 523 | 31 | 75.47 | 46.43 | 62% |
| 13 | Solid and Liquid Waste Management | 577 | 8 | 239 | 315 | 0.85 | 0.45 | 53% |
| 14 | Repair & maint of Pond/ Tank | 447 | 5 | 164 | 219 | 7.99 | 5.81 | 73% |
| 15 | Construction of Check Dam/Stop Dam | 389 | 0 | 192 | 160 | 12.20 | 8.73 | 72% |
| 16 | Construction of Bund | 375 | 0 | 168 | 165 | 8.39 | 5.58 | 67% |
| 17 | Construction of Tank | 358 | 7 | 115 | 124 | 18.81 | 12.93 | 69% |
| 18 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 337 | 7 | 161 | 115 | 11.40 | 7.92 | 70% |
| 19 | Construction of Crematorium | 298 | 5 | 239 | 18 | 5.53 | 4.55 | 82% |
| 20 | Construction of Trench | 293 | 0 | 196 | 68 | 6.86 | 4.96 | 72% |
| 21 | Community Sanitary Complex | 193 | 10 | 157 | 22 | 0.81 | 0.70 | 86% |
| 22 | Land Development | 186 | 11 | 129 | 15 | 7.10 | 3.67 | 52% |
| 23 | Cattle Shed | 179 | 2 | 73 | 54 | 6.43 | 5.28 | 82% |
| 24 | Construction of Play field | 161 | 2 | 104 | 21 | 4.58 | 2.37 | 52% |
| 25 | Constr of Aganwadi | 161 | 7 | 136 | 8 | 4.29 | 3.16 | 74% |
| 26 | Constr of Compound wall | 108 | 6 | 77 | 9 | 6.43 | 4.65 | 72% |
| 27 | Repair & Maint of Check Dam/Stop Dam | 108 | 1 | 42 | 60 | 0.91 | 0.61 | 68% |
| 28 | Constr of Kitchen Shed | 106 | 0 | 22 | 72 | 0.21 | 0.12 | 58% |
| 29 | Construction of building/workshed for SHG | 92 | 14 | 47 | 20 | 1.79 | 1.05 | 59% |
| 30 | Roof Water Harvesting on gov/panchayat bldg | 64 | 0 | 14 | 40 | 0.13 | 0.05 | 36% |
| 31 | Repair & maint of Water Harvesting Structures | 58 | 0 | 31 | 21 | 0.95 | 0.60 | 63% |
| 32 | Grass Land Development | 55 | 0 | 7 | 27 | 2.52 | 0.87 | 35% |
| 33 | Renovation of traditional water bodies | 51 | 0 | 38 | 1 | 1.44 | 0.93 | 65% |
| 34 | Terracing | 45 | 0 | 27 | 13 | 0.91 | 0.59 | 65% |
| 35 | Constr of GP Bhawan | 35 | 0 | 32 | 1 | 3.95 | 2.93 | 74% |
| 36 | Nursery Development | 22 | 0 | 21 | 0 | 0.89 | 0.50 | 56% |
| 37 | Repair & maint of Percolation Tank | 19 | 0 | 10 | 6 | 0.48 | 0.33 | 68% |
| 38 | Underground Dyke for Ground Water Recharge | 17 | 0 | 1 | 11 | 0.02 | 0.01 | 47% |
| 39 | Repair & maint of Road | 16 | 0 | 8 | 1 | 1.34 | 0.95 | 71% |
| 40 | Constr of Food Grain storage | 15 | 0 | 8 | 6 | 1.03 | 0.68 | 66% |
| 41 | Boulder Check/Gully Plug | 6 | 0 | 3 | 3 | 0.06 | 0.03 | 52% |
| 42 | Culvert | 6 | 0 | 6 | 0 | 0.05 | 0.05 | 96% |
| 43 | Repair & Maint of Bund | 3 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 44 | Bio-gas plant | 2 | 0 | 0 | 2 | 0.00 | 0.00 | 0% |
| 45 | Bio-Fertilizer | 2 | 0 | 0 | 1 | 0.02 | 0.00 | 0% |
| 46 | Constr of Gabion | 2 | 0 | 1 | 1 | 0.08 | 0.02 | 20% |
| 47 | Construction of Embankment | 2 | 0 | 1 | 1 | 0.13 | 0.13 | 99% |
| 48 | Construction of Other Community Building/Assets | 1 | 0 | 1 | 0 | 0.02 | 0.02 | 97% |
| Total | 42,347 | 2,941 | 28,308 | 5,292 | 494.93 | 320.46 |