| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 327 | 58.34 | 49.64 | 85% |
| 2 | Construction of Well | 32 | 79.04 | 70.54 | 89% |
| 3 | Construction of Road and Culvert | 23 | 94.46 | 53.44 | 57% |
| 4 | Constr of Cement Concrete Roads | 15 | 15.40 | 13.06 | 85% |
| 5 | Farm Pond | 12 | 19.43 | 11.35 | 58% |
| 6 | Construction of Check Dam/Stop Dam | 11 | 14.80 | 7.48 | 51% |
| 7 | Plantation | 6 | 20.10 | 1.80 | 9% |
| 8 | Well Recharge | 5 | 6.74 | 5.95 | 88% |
| 9 | Land Development | 3 | 13.44 | 12.12 | 90% |
| 10 | Repair & maint of Pond/ Tank | 2 | 1.85 | 1.11 | 60% |
| 11 | Construction of Trench | 1 | 1.08 | 0.64 | 59% |
| 12 | Construction of Crematorium | 1 | 1.96 | 1.58 | 81% |
| 13 | Construction of Percolation Tank | 1 | 3.33 | 2.67 | 80% |
| 14 | Construction of Tank | 1 | 4.71 | 2.82 | 60% |
| 15 | Culvert | 1 | 3.91 | 3.13 | 80% |
| 16 | Strengthening of Embankment | 1 | 2.78 | 2.62 | 94% |
| Total | 442 | 341.36 | 239.96 |