MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-20 07:03:41.950739
to
to
Reset filters
Scope
Works completed
385
Sanctioned (pure scheme)
₹5.43 Cr
Expenditure since inception
₹3.69 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
6 works
₹1.12 Cr sanctioned
₹26.50 L spent (24%)
02
Construction of Bund
44 works
₹1.02 Cr sanctioned
₹81.23 L spent (80%)
03
Construction of Check Dam/Stop Dam
31 works
₹89.49 L sanctioned
₹97.02 L spent (108%)
04
Repair & maint of Pond/ Tank
13 works
₹69.00 L sanctioned
₹52.65 L spent (76%)
05
Constr of Cement Concrete Roads
18 works
₹31.38 L sanctioned
₹15.88 L spent (51%)
06
Rural Housing
172 works
₹28.31 L sanctioned
₹27.78 L spent (98%)
07
Plantation
13 works
₹22.67 L sanctioned
₹7.98 L spent (35%)
08
Construction of Trench
6 works
₹20.57 L sanctioned
₹17.55 L spent (85%)
09
Construction of Play field
1 works
₹14.91 L sanctioned
₹6.95 L spent (47%)
10
Land Development
3 works
₹10.59 L sanctioned
₹7.03 L spent (66%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 172 0.28 0.28
98%
2 Construction of Bund 44 1.02 0.81
80%
3 Construction of Check Dam/Stop Dam 31 0.89 0.97
108%
4 Constr of Cement Concrete Roads 18 0.31 0.16
51%
5 Repair & maint of Pond/ Tank 13 0.69 0.53
76%
6 Plantation 13 0.23 0.08
35%
7 Solid and Liquid Waste Management 12 0.02 0.02
89%
8 Construction of Recharge Pits 10 0.01 0.00
16%
9 Farm Pond 9 0.06 0.05
87%
10 Construction of Well 9 0.06 0.04
70%
11 Cattle Shed 9 0.08 0.08
94%
12 Construction of NADEP/Vermi Compost Pit 9 0.00 0.00
98%
13 Construction of Road and Culvert 6 1.12 0.26
24%
14 Construction of Trench 6 0.21 0.18
85%
15 Construction of Tank 5 0.01 0.00
37%
16 Boulder Check/Gully Plug 4 0.02 0.01
28%
17 Community Sanitary Complex 4 0.01 0.01
90%
18 Land Development 3 0.11 0.07
66%
19 Construction of Toilets 2 0.00 0.00
83%
20 Construction of Play field 1 0.15 0.07
47%
21 Construction of building/workshed for SHG 1 0.01 0.01
96%
22 Goat Shelter 1 0.01 0.01
89%
23 Repair & Maint of Community infrastructure 1 0.03 0.02
86%
24 Constr of Compound wall 1 0.00 0.00
90%
25 Construction of Crematorium 1 0.10 0.03
31%
Total 385 5.43 3.69
All 25 rows (zero-value rows hidden) ⇩ Export to Excel