Showcase — Completed Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
to
Reset filters
Scope
Works completed
411
Sanctioned (pure scheme)
₹3.10 Cr
Expenditure since inception
₹2.10 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
14 works
₹47.58 L sanctioned
₹41.00 L spent (86%)
02
Construction of Check Dam/Stop Dam
20 works
₹40.38 L sanctioned
₹18.85 L spent (47%)
03
Rural Housing
210 works
₹38.47 L sanctioned
₹37.47 L spent (97%)
04
Construction of Road and Culvert
9 works
₹36.78 L sanctioned
₹23.88 L spent (65%)
05
Construction of Well
14 works
₹32.69 L sanctioned
₹17.41 L spent (53%)
06
Constr of Cement Concrete Roads
12 works
₹23.90 L sanctioned
₹15.32 L spent (64%)
07
Farm Pond
7 works
₹20.27 L sanctioned
₹18.69 L spent (92%)
08
Plantation
8 works
₹19.11 L sanctioned
₹1.37 L spent (7%)
09
Constr of Gabion
1 works
₹14.95 L sanctioned
₹12.29 L spent (82%)
10
Construction of Toilets
89 works
₹5.51 L sanctioned
₹5.25 L spent (95%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 210 38.47 37.47
97%
2 Construction of Toilets 89 5.51 5.25
95%
3 Construction of Check Dam/Stop Dam 20 40.38 18.85
47%
4 Construction of Well 14 32.69 17.41
53%
5 Construction of Tank 14 47.58 41.00
86%
6 Constr of Cement Concrete Roads 12 23.90 15.32
64%
7 Land Development 11 3.77 2.44
65%
8 Construction of Road and Culvert 9 36.78 23.88
65%
9 Plantation 8 19.11 1.37
7%
10 Farm Pond 7 20.27 18.69
92%
11 Boulder Check/Gully Plug 2 2.01 0.83
41%
12 Construction of Crematorium 2 4.25 3.61
85%
13 Construction of NADEP/Vermi Compost Pit 2 0.29 0.08
28%
14 Repair & maint of Pond/ Tank 2 3.88 3.52
91%
15 Construction of Recharge Pits 1 2.55 0.22
9%
16 Solid and Liquid Waste Management 1 0.14 0.04
25%
17 Construction of Trench 1 1.77 0.39
22%
18 Construction of Play field 1 2.13 0.70
33%
19 Construction of Bund 1 2.30 1.97
86%
20 Constr of Gabion 1 14.95 12.29
82%
21 Constr of Aganwadi 1 1.80 1.79
100%
22 Renovation of traditional water bodies 1 4.97 2.31
46%
23 Community Sanitary Complex 1 0.86 0.42
49%
Total 411 310.36 209.88
All 23 rows (zero-value rows hidden) ⇩ Export to Excel