Showcase — Completed Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
17 works
₹1.11 Cr sanctioned
₹43.73 L spent (39%)
02
Construction of Check Dam/Stop Dam
5 works
₹44.73 L sanctioned
₹43.72 L spent (98%)
03
Construction of Bund
2 works
₹34.85 L sanctioned
₹28.64 L spent (82%)
04
Constr of Cement Concrete Roads
34 works
₹27.13 L sanctioned
₹25.23 L spent (93%)
05
Land Development
12 works
₹25.60 L sanctioned
₹5.62 L spent (22%)
06
Plantation
8 works
₹23.68 L sanctioned
₹65,105 spent (3%)
07
Boulder Check/Gully Plug
1 works
₹8.99 L sanctioned
₹8.05 L spent (89%)
08
Construction of NADEP/Vermi Compost Pit
12 works
₹8.32 L sanctioned
₹6.71 L spent (81%)
09
Rural Housing
50 works
₹7.75 L sanctioned
₹6.98 L spent (90%)
10
Cattle Shed
6 works
₹5.47 L sanctioned
₹4.02 L spent (73%)