Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
22 works
₹78.76 L sanctioned
₹50.60 L spent (64%)
02
Construction of Check Dam/Stop Dam
7 works
₹76.42 L sanctioned
₹45.64 L spent (60%)
03
Construction of Bund
10 works
₹48.10 L sanctioned
₹28.44 L spent (59%)
04
Constr of Cement Concrete Roads
36 works
₹31.64 L sanctioned
₹21.40 L spent (68%)
05
Construction of Road and Culvert
2 works
₹26.15 L sanctioned
₹12.61 L spent (48%)
06
Repair & Maint of Community infrastructure
1 works
₹10.78 L sanctioned
₹5.03 L spent (47%)
07
Constr of Aganwadi
3 works
₹9.90 L sanctioned
₹9.61 L spent (97%)
08
Plantation
3 works
₹7.26 L sanctioned
₹1.76 L spent (24%)
09
Cattle Shed
6 works
₹6.95 L sanctioned
₹5.81 L spent (84%)
10
Land Development
1 works
₹5.54 L sanctioned
₹3.23 L spent (58%)