Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Works completed
79
Sanctioned (pure scheme)
₹46.10 L
Expenditure since inception
₹31.19 L
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
29 works
₹16.54 L sanctioned
₹13.94 L spent (84%)
02
Construction of Road and Culvert
1 works
₹9.01 L sanctioned
₹5.41 L spent (60%)
03
Construction of Canal
2 works
₹5.58 L sanctioned
₹4.08 L spent (73%)
04
Cattle Shed
4 works
₹4.64 L sanctioned
₹2.46 L spent (53%)
05
Land Development
10 works
₹2.44 L sanctioned
₹1.22 L spent (50%)
06
Construction of Crematorium
1 works
₹1.80 L sanctioned
₹5,160 spent (3%)
07
Construction of NADEP/Vermi Compost Pit
10 works
₹1.78 L sanctioned
₹1.40 L spent (79%)
08
Solid and Liquid Waste Management
13 works
₹1.30 L sanctioned
₹1.23 L spent (95%)
09
Other Works
1 works
₹1.16 L sanctioned
₹85,086 spent (73%)
10
Construction of Bund
1 works
₹98,000 sanctioned
₹10,320 spent (11%)