Showcase — Completed Works
Rollup last refreshed: 2026-10-15 06:57:05.982177
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
12 works
₹94.27 L sanctioned
₹55.85 L spent (59%)
02
Constr of Cement Concrete Roads
43 works
₹34.74 L sanctioned
₹29.89 L spent (86%)
03
Construction of Bund
49 works
₹25.01 L sanctioned
₹14.71 L spent (59%)
04
Construction of Percolation Tank
2 works
₹9.98 L sanctioned
₹10.21 L spent (102%)
05
Cattle Shed
5 works
₹5.07 L sanctioned
₹4.65 L spent (92%)
06
Land Development
37 works
₹4.65 L sanctioned
₹5.38 L spent (116%)
07
Solid and Liquid Waste Management
80 works
₹4.19 L sanctioned
₹3.94 L spent (94%)
08
Construction of Toilets
74 works
₹3.64 L sanctioned
₹2.73 L spent (75%)
09
Construction of Trench
2 works
₹3.40 L sanctioned
₹2.43 L spent (72%)
10
Plantation
1 works
₹3.35 L sanctioned
₹21,672 spent (6%)