Showcase — Completed Works
Rollup last refreshed: 2026-10-13 07:05:51.512495
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
31 works
₹74.92 L sanctioned
₹68.51 L spent (91%)
02
Works for Flood Control and Protection
13 works
₹52.17 L sanctioned
₹37.95 L spent (73%)
03
Plantation
10 works
₹41.56 L sanctioned
₹25.99 L spent (63%)
04
Construction of Bund
5 works
₹38.77 L sanctioned
₹30.63 L spent (79%)
05
Solid and Liquid Waste Management
9 works
₹37.13 L sanctioned
₹28.56 L spent (77%)
06
Construction of Other Community Building/Assets
1 works
₹27.72 L sanctioned
₹27.70 L spent (100%)
07
Construction of Percolation Tank
1 works
₹19.47 L sanctioned
₹16.53 L spent (85%)
08
Cattle Shed
21 works
₹15.23 L sanctioned
₹13.15 L spent (86%)
09
Constr of Cement Concrete Roads
38 works
₹14.90 L sanctioned
₹15.18 L spent (102%)
10
Construction of Trench
4 works
₹11.16 L sanctioned
₹8.15 L spent (73%)