Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
7 works
₹38.47 L sanctioned
₹31.77 L spent (83%)
02
Construction of Check Dam/Stop Dam
11 works
₹35.38 L sanctioned
₹32.96 L spent (93%)
03
Solid and Liquid Waste Management
8 works
₹32.84 L sanctioned
₹29.96 L spent (91%)
04
Construction of Road and Culvert
7 works
₹28.62 L sanctioned
₹14.09 L spent (49%)
05
Constr of Aganwadi
1 works
₹27.72 L sanctioned
₹25.90 L spent (93%)
06
Constr of Cement Concrete Roads
30 works
₹24.71 L sanctioned
₹15.06 L spent (61%)
07
Plantation
10 works
₹24.39 L sanctioned
₹6.88 L spent (28%)
08
Rural Housing
134 works
₹23.11 L sanctioned
₹21.82 L spent (94%)
09
Construction of NADEP/Vermi Compost Pit
170 works
₹22.18 L sanctioned
₹20.66 L spent (93%)
10
Constr of GP Bhawan
2 works
₹15.06 L sanctioned
₹11.87 L spent (79%)