Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
4 works
₹46.36 L sanctioned
₹28.38 L spent (61%)
02
Construction of Check Dam/Stop Dam
5 works
₹17.27 L sanctioned
₹14.14 L spent (82%)
03
Constr of Cement Concrete Roads
13 works
₹10.45 L sanctioned
₹9.45 L spent (90%)
04
Plantation
5 works
₹8.36 L sanctioned
₹1.03 L spent (12%)
05
Construction of Percolation Tank
3 works
₹7.95 L sanctioned
₹5.72 L spent (72%)
06
Land Development
2 works
₹7.90 L sanctioned
₹5.46 L spent (69%)
07
Construction of Trench
1 works
₹6.95 L sanctioned
₹3.47 L spent (50%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
5 works
₹4.34 L sanctioned
₹3.27 L spent (75%)
09
Cattle Shed
10 works
₹4.10 L sanctioned
₹3.91 L spent (95%)
10
Rural Housing
22 works
₹3.74 L sanctioned
₹3.57 L spent (96%)