Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
8 works
₹2.37 Cr sanctioned
₹3.23 L spent (1%)
02
Construction of Road and Culvert
13 works
₹88.86 L sanctioned
₹57.16 L spent (64%)
03
Construction of Tank
4 works
₹41.43 L sanctioned
₹40.41 L spent (98%)
04
Construction of Recharge Pits
12 works
₹37.27 L sanctioned
₹32.07 L spent (86%)
05
Construction of Check Dam/Stop Dam
21 works
₹29.41 L sanctioned
₹16.64 L spent (57%)
06
Culvert
2 works
₹14.16 L sanctioned
₹14.10 L spent (100%)
07
Land Development
2 works
₹13.98 L sanctioned
₹13.61 L spent (97%)
08
Constr of Cement Concrete Roads
22 works
₹13.71 L sanctioned
₹12.51 L spent (91%)
09
Construction of Trench
5 works
₹7.93 L sanctioned
₹5.23 L spent (66%)
10
Farm Pond
6 works
₹6.13 L sanctioned
₹4.33 L spent (71%)