Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
13 works
₹85.96 L sanctioned
₹51.97 L spent (60%)
02
Constr of Cement Concrete Roads
26 works
₹79.49 L sanctioned
₹42.70 L spent (54%)
03
Construction of Check Dam/Stop Dam
28 works
₹34.84 L sanctioned
₹23.03 L spent (66%)
04
Constr of Gabion
3 works
₹26.03 L sanctioned
₹21.48 L spent (83%)
05
Plantation
9 works
₹19.20 L sanctioned
₹5.17 L spent (27%)
06
Rural Housing
94 works
₹16.34 L sanctioned
₹15.30 L spent (94%)
07
Construction of Bund
14 works
₹15.97 L sanctioned
₹16.60 L spent (104%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹14.59 L sanctioned
₹9.14 L spent (63%)
09
Land Development
2 works
₹9.50 L sanctioned
₹6.84 L spent (72%)
10
Construction of Percolation Tank
4 works
₹8.84 L sanctioned
₹6.07 L spent (69%)