Showcase — Completed Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
19 works
₹88.36 L sanctioned
₹32.87 L spent (37%)
02
Plantation
16 works
₹59.93 L sanctioned
₹40.95 L spent (68%)
03
Rural Housing
206 works
₹40.50 L sanctioned
₹39.29 L spent (97%)
04
Constr of Cement Concrete Roads
21 works
₹39.43 L sanctioned
₹22.90 L spent (58%)
05
Construction of Tank
2 works
₹22.53 L sanctioned
₹21.12 L spent (94%)
06
Repair & maint of Pond/ Tank
4 works
₹21.50 L sanctioned
₹17.50 L spent (81%)
07
Culvert
4 works
₹17.07 L sanctioned
₹12.96 L spent (76%)
08
Construction of Check Dam/Stop Dam
3 works
₹10.88 L sanctioned
₹1.77 L spent (16%)
09
Construction of Trench
1 works
₹6.70 L sanctioned
₹5.59 L spent (84%)
10
Solid and Liquid Waste Management
1 works
₹6.51 L sanctioned
₹5.60 L spent (86%)