Showcase — Completed Works
Rollup last refreshed: 2026-10-01 08:37:11.749328
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
11 works
₹91.19 L sanctioned
₹87.68 L spent (96%)
02
Construction of Road and Culvert
10 works
₹89.14 L sanctioned
₹76.19 L spent (85%)
03
Construction of Tank
5 works
₹72.46 L sanctioned
₹70.58 L spent (97%)
04
Construction of Check Dam/Stop Dam
12 works
₹58.91 L sanctioned
₹50.78 L spent (86%)
05
Construction of Well
15 works
₹36.96 L sanctioned
₹27.48 L spent (74%)
06
Culvert
5 works
₹36.25 L sanctioned
₹30.07 L spent (83%)
07
Farm Pond
12 works
₹30.24 L sanctioned
₹19.62 L spent (65%)
08
Rural Housing
175 works
₹29.56 L sanctioned
₹28.77 L spent (97%)
09
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
6 works
₹24.00 L sanctioned
₹22.27 L spent (93%)
10
Constr of Cement Concrete Roads
15 works
₹19.85 L sanctioned
₹14.55 L spent (73%)