Showcase — Completed Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Percolation Tank
14 works
₹1.14 Cr sanctioned
₹1.06 Cr spent (94%)
02
Repair & maint of Pond/ Tank
8 works
₹70.76 L sanctioned
₹69.42 L spent (98%)
03
Construction of Check Dam/Stop Dam
22 works
₹53.22 L sanctioned
₹42.93 L spent (81%)
04
Construction of Road and Culvert
6 works
₹35.48 L sanctioned
₹29.71 L spent (84%)
05
Construction of Well
13 works
₹35.05 L sanctioned
₹30.76 L spent (88%)
06
Construction of Bund
4 works
₹28.94 L sanctioned
₹28.89 L spent (100%)
07
Construction of Play field
2 works
₹20.70 L sanctioned
₹20.21 L spent (98%)
08
Constr of Cement Concrete Roads
18 works
₹19.56 L sanctioned
₹11.99 L spent (61%)
09
Plantation
6 works
₹17.98 L sanctioned
₹6.03 L spent (34%)
10
Rural Housing
105 works
₹17.32 L sanctioned
₹16.93 L spent (98%)