Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
69 works
₹1.56 Cr sanctioned
₹1.41 Cr spent (90%)
02
Construction of Bund
16 works
₹1.18 Cr sanctioned
₹1.09 Cr spent (92%)
03
Construction of Check Dam/Stop Dam
14 works
₹65.81 L sanctioned
₹56.54 L spent (86%)
04
Rural Housing
318 works
₹56.91 L sanctioned
₹55.04 L spent (97%)
05
Construction of Road and Culvert
9 works
₹47.83 L sanctioned
₹30.23 L spent (63%)
06
Construction of Trench
4 works
₹30.00 L sanctioned
₹26.40 L spent (88%)
07
Construction of Percolation Tank
4 works
₹29.64 L sanctioned
₹23.41 L spent (79%)
08
Land Development
86 works
₹27.36 L sanctioned
₹24.20 L spent (88%)
09
Grass Land Development
2 works
₹25.90 L sanctioned
₹25.56 L spent (99%)
10
Construction of Tank
12 works
₹25.71 L sanctioned
₹25.24 L spent (98%)