Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
2 works
₹28.89 L sanctioned
₹25.86 L spent (89%)
02
Constr of Cement Concrete Roads
10 works
₹18.45 L sanctioned
₹17.78 L spent (96%)
03
Rural Housing
81 works
₹13.68 L sanctioned
₹13.42 L spent (98%)
04
Construction of Road and Culvert
8 works
₹12.03 L sanctioned
₹26.00 L spent (216%)
05
Land Development
2 works
₹9.95 L sanctioned
₹3.74 L spent (38%)
06
Construction of Crematorium
2 works
₹8.91 L sanctioned
₹3.42 L spent (38%)
07
Construction of building/workshed for SHG
1 works
₹7.80 L sanctioned
₹1.82 L spent (23%)
08
Farm Pond
25 works
₹7.43 L sanctioned
₹4.34 L spent (58%)
09
Plantation
4 works
₹7.19 L sanctioned
₹1.89 L spent (26%)
10
Construction of Well
2 works
₹6.88 L sanctioned
₹4.23 L spent (62%)