Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
7 works
₹83.16 L sanctioned
₹67.41 L spent (81%)
02
Rural Housing
344 works
₹65.65 L sanctioned
₹65.66 L spent (100%)
03
Construction of Check Dam/Stop Dam
9 works
₹44.20 L sanctioned
₹42.57 L spent (96%)
04
Construction of Road and Culvert
13 works
₹32.67 L sanctioned
₹36.83 L spent (113%)
05
Constr of Cement Concrete Roads
25 works
₹28.93 L sanctioned
₹43.27 L spent (150%)
06
Plantation
306 works
₹16.46 L sanctioned
₹18.91 L spent (115%)
07
Farm Pond
8 works
₹13.47 L sanctioned
₹8.34 L spent (62%)
08
Construction of Percolation Tank
2 works
₹9.66 L sanctioned
₹11.53 L spent (119%)
09
Construction of Well
21 works
₹8.06 L sanctioned
₹19.50 L spent (242%)
10
Renovation of traditional water bodies
6 works
₹7.78 L sanctioned
₹3.22 L spent (41%)