Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
26 works
₹67.45 L sanctioned
₹77.42 L spent (115%)
02
Construction of Road and Culvert
13 works
₹49.87 L sanctioned
₹59.92 L spent (120%)
03
Rural Housing
204 works
₹32.86 L sanctioned
₹32.66 L spent (99%)
04
Plantation
15 works
₹24.87 L sanctioned
₹21.28 L spent (86%)
05
Construction of Percolation Tank
3 works
₹15.45 L sanctioned
₹14.75 L spent (95%)
06
Constr of Cement Concrete Roads
13 works
₹9.95 L sanctioned
₹10.28 L spent (103%)
07
Construction of Check Dam/Stop Dam
11 works
₹8.59 L sanctioned
₹25.17 L spent (293%)
08
Construction of Recharge Pits
4 works
₹6.79 L sanctioned
₹6.00 L spent (88%)
09
Farm Pond
3 works
₹5.67 L sanctioned
₹8.64 L spent (152%)
10
Construction of Play field
1 works
₹4.22 L sanctioned
₹4.20 L spent (100%)