Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Tank
24 works
₹94.45 L sanctioned
₹75.59 L spent (80%)
02
Construction of Well
25 works
₹77.59 L sanctioned
₹63.69 L spent (82%)
03
Plantation
31 works
₹70.85 L sanctioned
₹27.43 L spent (39%)
04
Cattle Shed
56 works
₹56.71 L sanctioned
₹45.33 L spent (80%)
05
Construction of Trench
8 works
₹45.69 L sanctioned
₹38.87 L spent (85%)
06
Rural Housing
224 works
₹42.29 L sanctioned
₹40.96 L spent (97%)
07
Farm Pond
13 works
₹29.97 L sanctioned
₹30.33 L spent (101%)
08
Construction of Road and Culvert
2 works
₹25.41 L sanctioned
₹13.31 L spent (52%)
09
Construction of Check Dam/Stop Dam
3 works
₹15.35 L sanctioned
₹14.43 L spent (94%)
10
Repair & maint of Pond/ Tank
4 works
₹13.46 L sanctioned
₹10.69 L spent (79%)