Showcase — Completed Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
12 works
₹53.18 L sanctioned
₹28.19 L spent (53%)
02
Construction of Road and Culvert
7 works
₹49.29 L sanctioned
₹30.94 L spent (63%)
03
Construction of Check Dam/Stop Dam
4 works
₹43.61 L sanctioned
₹42.22 L spent (97%)
04
Cattle Shed
1 works
₹37.85 L sanctioned
₹37.08 L spent (98%)
05
Construction of Bund
3 works
₹36.29 L sanctioned
₹32.44 L spent (89%)
06
Construction of Well
20 works
₹31.95 L sanctioned
₹27.16 L spent (85%)
07
Construction of Tank
7 works
₹30.44 L sanctioned
₹28.42 L spent (93%)
08
Construction of Trench
4 works
₹14.98 L sanctioned
₹10.49 L spent (70%)
09
Constr of Cement Concrete Roads
8 works
₹14.64 L sanctioned
₹7.99 L spent (55%)
10
Land Development
2 works
₹13.67 L sanctioned
₹10.71 L spent (78%)