Showcase — Completed Works
Rollup last refreshed: 2026-08-23 08:31:42.168333
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
6 works
₹65.29 L sanctioned
₹49.22 L spent (75%)
02
Constr of Cement Concrete Roads
39 works
₹37.79 L sanctioned
₹32.96 L spent (87%)
03
Rural Housing
121 works
₹23.98 L sanctioned
₹23.96 L spent (100%)
04
Plantation
7 works
₹15.55 L sanctioned
₹1.19 L spent (8%)
05
Constr of Food Grain storage
1 works
₹10.45 L sanctioned
₹3,268 spent (0%)
06
Construction of Percolation Tank
3 works
₹9.27 L sanctioned
₹7.19 L spent (78%)
07
Constr of Aganwadi
1 works
₹7.80 L sanctioned
₹1,752 spent (0%)
08
Construction of Trench
5 works
₹6.91 L sanctioned
₹5.93 L spent (86%)
09
Construction of building/workshed for SHG
1 works
₹6.47 L sanctioned
₹6.00 L spent (93%)
10
Farm Pond
2 works
₹6.43 L sanctioned
₹3.91 L spent (61%)