Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
11 works
₹2.30 Cr sanctioned
₹82.04 L spent (36%)
02
Construction of Well
72 works
₹1.68 Cr sanctioned
₹1.85 Cr spent (110%)
03
Construction of Tank
3 works
₹54.11 L sanctioned
₹50.80 L spent (94%)
04
Construction of Check Dam/Stop Dam
6 works
₹24.95 L sanctioned
₹24.64 L spent (99%)
05
Construction of Trench
2 works
₹21.93 L sanctioned
₹19.89 L spent (91%)
06
Construction of Percolation Tank
5 works
₹16.50 L sanctioned
₹15.49 L spent (94%)
07
Constr of Aganwadi
2 works
₹15.60 L sanctioned
₹4.96 L spent (32%)
08
Construction of Embankment
1 works
₹14.87 L sanctioned
₹14.86 L spent (100%)
09
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
2 works
₹13.44 L sanctioned
₹9.56 L spent (71%)
10
Constr of GP Bhawan
1 works
₹12.85 L sanctioned
₹8.86 L spent (69%)