Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
19 works
₹94.43 L sanctioned
₹80.31 L spent (85%)
02
Construction of Trench
5 works
₹21.65 L sanctioned
₹19.49 L spent (90%)
03
Constr of Cement Concrete Roads
10 works
₹16.06 L sanctioned
₹11.46 L spent (71%)
04
Rural Housing
59 works
₹11.45 L sanctioned
₹10.98 L spent (96%)
05
Renovation of traditional water bodies
5 works
₹9.34 L sanctioned
₹6.59 L spent (71%)
06
Construction of Tank
2 works
₹8.18 L sanctioned
₹8.15 L spent (100%)
07
Constr of Gabion
2 works
₹7.06 L sanctioned
₹6.48 L spent (92%)
08
Land Development
3 works
₹6.51 L sanctioned
₹4.23 L spent (65%)
09
Plantation
4 works
₹5.79 L sanctioned
₹4.11 L spent (71%)
10
Construction of Percolation Tank
2 works
₹5.16 L sanctioned
₹5.16 L spent (100%)