Showcase — Completed Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
20 works
₹58.02 L sanctioned
₹37.60 L spent (65%)
02
Terracing
4 works
₹23.63 L sanctioned
₹21.10 L spent (89%)
03
Construction of Trench
6 works
₹19.06 L sanctioned
₹16.06 L spent (84%)
04
Construction of Check Dam/Stop Dam
15 works
₹15.55 L sanctioned
₹43.44 L spent (279%)
05
Construction of Well
8 works
₹14.14 L sanctioned
₹13.80 L spent (98%)
06
Constr of Compound wall
2 works
₹10.73 L sanctioned
₹10.71 L spent (100%)
07
Plantation
4 works
₹7.60 L sanctioned
₹3.80 L spent (50%)
08
Rural Housing
39 works
₹7.12 L sanctioned
₹5.07 L spent (71%)
09
Construction of Percolation Tank
1 works
₹4.94 L sanctioned
₹3.96 L spent (80%)
10
Constr of Cement Concrete Roads
3 works
₹4.00 L sanctioned
₹3.80 L spent (95%)