Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
513 works
₹16.25 Cr sanctioned
₹6.05 Cr spent (37%)
02
Construction of Check Dam/Stop Dam
405 works
₹14.06 Cr sanctioned
₹13.67 Cr spent (97%)
03
Rural Housing
4,479 works
₹7.91 Cr sanctioned
₹7.69 Cr spent (97%)
04
Construction of Well
816 works
₹7.82 Cr sanctioned
₹8.49 Cr spent (108%)
05
Construction of Road and Culvert
180 works
₹7.72 Cr sanctioned
₹5.62 Cr spent (73%)
06
Construction of Percolation Tank
53 works
₹4.22 Cr sanctioned
₹3.69 Cr spent (88%)
07
Constr of Cement Concrete Roads
216 works
₹2.44 Cr sanctioned
₹2.28 Cr spent (93%)
08
Construction of Trench
111 works
₹1.96 Cr sanctioned
₹1.56 Cr spent (80%)
09
Farm Pond
208 works
₹1.46 Cr sanctioned
₹3.35 Cr spent (230%)
10
Cattle Shed
27 works
₹1.28 Cr sanctioned
₹1.25 Cr spent (97%)