Showcase — Completed Works
Rollup last refreshed: 2026-10-14 07:05:44.899714
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
679 works
₹42.28 Cr sanctioned
₹27.95 Cr spent (66%)
02
Plantation
877 works
₹30.03 Cr sanctioned
₹12.04 Cr spent (40%)
03
Construction of Check Dam/Stop Dam
722 works
₹29.11 Cr sanctioned
₹25.77 Cr spent (89%)
04
Rural Housing
10,797 works
₹22.45 Cr sanctioned
₹19.98 Cr spent (89%)
05
Construction of Trench
485 works
₹16.05 Cr sanctioned
₹13.15 Cr spent (82%)
06
Farm Pond
851 works
₹11.65 Cr sanctioned
₹9.25 Cr spent (79%)
07
Construction of Bund
1,490 works
₹9.61 Cr sanctioned
₹7.84 Cr spent (82%)
08
Construction of Well
754 works
₹8.11 Cr sanctioned
₹6.65 Cr spent (82%)
09
Construction of Percolation Tank
99 works
₹6.38 Cr sanctioned
₹5.52 Cr spent (87%)
10
Constr of Cement Concrete Roads
283 works
₹4.97 Cr sanctioned
₹4.40 Cr spent (88%)