Showcase — Completed Works
Rollup last refreshed: 2026-10-16 08:36:19.743515
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Terracing
15 works
₹35.45 L sanctioned
₹29.72 L spent (84%)
02
Construction of Road and Culvert
7 works
₹34.76 L sanctioned
₹33.55 L spent (97%)
03
Construction of Well
27 works
₹32.31 L sanctioned
₹32.06 L spent (99%)
04
Construction of Trench
7 works
₹28.04 L sanctioned
₹22.24 L spent (79%)
05
Construction of Check Dam/Stop Dam
6 works
₹25.40 L sanctioned
₹26.57 L spent (105%)
06
Plantation
8 works
₹23.64 L sanctioned
₹8.21 L spent (35%)
07
Well Recharge
4 works
₹13.99 L sanctioned
₹8.91 L spent (64%)
08
Rural Housing
62 works
₹13.49 L sanctioned
₹13.47 L spent (100%)
09
Cattle Shed
17 works
₹13.04 L sanctioned
₹9.60 L spent (74%)
10
Constr of Cement Concrete Roads
9 works
₹12.79 L sanctioned
₹11.49 L spent (90%)