Showcase — Completed Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
15 works
₹1.55 Cr sanctioned
₹1.02 Cr spent (66%)
02
Construction of Well
49 works
₹80.21 L sanctioned
₹69.84 L spent (87%)
03
Construction of Check Dam/Stop Dam
37 works
₹41.71 L sanctioned
₹21.93 L spent (53%)
04
Construction of Trench
8 works
₹37.37 L sanctioned
₹29.91 L spent (80%)
05
Farm Pond
6 works
₹21.01 L sanctioned
₹15.60 L spent (74%)
06
Land Development
22 works
₹12.50 L sanctioned
₹7.31 L spent (58%)
07
Constr of Cement Concrete Roads
8 works
₹12.42 L sanctioned
₹10.29 L spent (83%)
08
Plantation
5 works
₹11.91 L sanctioned
₹5.31 L spent (45%)
09
Construction of Tank
1 works
₹11.71 L sanctioned
₹8.87 L spent (76%)
10
Construction of Percolation Tank
2 works
₹8.83 L sanctioned
₹7.75 L spent (88%)