Showcase — Completed Works
Rollup last refreshed: 2026-09-23 07:03:14.247027
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
46 works
₹1.18 Cr sanctioned
₹1.06 Cr spent (90%)
02
Construction of Road and Culvert
12 works
₹71.05 L sanctioned
₹54.12 L spent (76%)
03
Rural Housing
181 works
₹31.40 L sanctioned
₹30.83 L spent (98%)
04
Construction of Trench
10 works
₹24.79 L sanctioned
₹21.69 L spent (87%)
05
Construction of Check Dam/Stop Dam
13 works
₹24.57 L sanctioned
₹18.67 L spent (76%)
06
Cattle Shed
20 works
₹23.60 L sanctioned
₹13.76 L spent (58%)
07
Constr of Cement Concrete Roads
13 works
₹22.31 L sanctioned
₹13.48 L spent (60%)
08
Construction of Recharge Pits
2 works
₹8.78 L sanctioned
₹8.33 L spent (95%)
09
Construction of Crematorium
4 works
₹8.50 L sanctioned
₹6.58 L spent (77%)
10
Plantation
2 works
₹6.70 L sanctioned
₹10,816 spent (2%)