Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
26 works
₹2.16 Cr sanctioned
₹1.55 Cr spent (72%)
02
Construction of Well
59 works
₹1.45 Cr sanctioned
₹1.28 Cr spent (88%)
03
Construction of Check Dam/Stop Dam
22 works
₹77.01 L sanctioned
₹55.33 L spent (72%)
04
Land Development
17 works
₹58.47 L sanctioned
₹30.88 L spent (53%)
05
Cattle Shed
12 works
₹50.83 L sanctioned
₹46.36 L spent (91%)
06
Construction of Percolation Tank
35 works
₹47.72 L sanctioned
₹33.91 L spent (71%)
07
Constr of Cement Concrete Roads
24 works
₹32.28 L sanctioned
₹26.72 L spent (83%)
08
Construction of Recharge Pits
10 works
₹31.20 L sanctioned
₹30.41 L spent (97%)
09
Rural Housing
147 works
₹26.29 L sanctioned
₹25.88 L spent (98%)
10
Farm Pond
14 works
₹21.68 L sanctioned
₹10.26 L spent (47%)