Showcase — Completed Works
Rollup last refreshed: 2026-10-16 08:49:07.017331
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
119 works
₹24.07 L sanctioned
₹23.31 L spent (97%)
02
Construction of Well
15 works
₹19.54 L sanctioned
₹28.57 L spent (146%)
03
Construction of Road and Culvert
2 works
₹16.40 L sanctioned
₹19,899 spent (1%)
04
Constr of Cement Concrete Roads
19 works
₹13.10 L sanctioned
₹11.10 L spent (85%)
05
Construction of Check Dam/Stop Dam
2 works
₹12.12 L sanctioned
₹2.77 L spent (23%)
06
Construction of Trench
6 works
₹8.81 L sanctioned
₹3.98 L spent (45%)
07
Plantation
2 works
₹6.03 L sanctioned
₹83,474 spent (14%)
08
Construction of Crematorium
3 works
₹5.88 L sanctioned
₹5.34 L spent (91%)
09
Construction of Toilets
49 works
₹5.37 L sanctioned
₹5.31 L spent (99%)
10
Solid and Liquid Waste Management
4 works
₹4.49 L sanctioned
₹3.19 L spent (71%)