Showcase — Completed Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
10 works
₹26.49 L sanctioned
₹15.17 L spent (57%)
02
Construction of Road and Culvert
3 works
₹18.76 L sanctioned
₹21.09 L spent (112%)
03
Rural Housing
97 works
₹15.49 L sanctioned
₹15.29 L spent (99%)
04
Constr of Cement Concrete Roads
14 works
₹12.82 L sanctioned
₹8.26 L spent (64%)
05
Farm Pond
3 works
₹10.28 L sanctioned
₹8.37 L spent (81%)
06
Land Development
21 works
₹6.33 L sanctioned
₹4.25 L spent (67%)
07
Goat Shelter
5 works
₹2.80 L sanctioned
₹2.03 L spent (72%)
08
Construction of Bund
1 works
₹2.67 L sanctioned
₹64,680 spent (24%)
09
Construction of Embankment
1 works
₹2.48 L sanctioned
₹2.24 L spent (90%)
10
Constr of Aganwadi
1 works
₹1.80 L sanctioned
₹1.57 L spent (87%)