Showcase — Completed Works
Rollup last refreshed: 2026-08-27 14:06:46.546602
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
6 works
₹24.84 L sanctioned
₹26.42 L spent (106%)
02
Repair & maint of Pond/ Tank
7 works
₹23.97 L sanctioned
₹12.95 L spent (54%)
03
Construction of Well
12 works
₹23.47 L sanctioned
₹14.36 L spent (61%)
04
Construction of Check Dam/Stop Dam
14 works
₹16.99 L sanctioned
₹10.04 L spent (59%)
05
Plantation
21 works
₹16.76 L sanctioned
₹10.00 L spent (60%)
06
Repair & maint of Road
2 works
₹14.70 L sanctioned
₹11.92 L spent (81%)
07
Construction of Trench
4 works
₹14.58 L sanctioned
₹2.14 L spent (15%)
08
Land Development
16 works
₹12.02 L sanctioned
₹5.82 L spent (48%)
09
Constr of Cement Concrete Roads
17 works
₹10.80 L sanctioned
₹11.01 L spent (102%)
10
Construction of Bund
5 works
₹8.34 L sanctioned