Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
407 works
₹70.37 L sanctioned
₹70.07 L spent (100%)
02
Construction of Tank
5 works
₹61.00 L sanctioned
₹52.29 L spent (86%)
03
Construction of Trench
8 works
₹52.78 L sanctioned
₹37.29 L spent (71%)
04
Construction of Road and Culvert
16 works
₹42.02 L sanctioned
₹61.87 L spent (147%)
05
Construction of Check Dam/Stop Dam
7 works
₹32.59 L sanctioned
₹31.20 L spent (96%)
06
Plantation
7 works
₹28.38 L sanctioned
₹7.96 L spent (28%)
07
Construction of Percolation Tank
1 works
₹12.67 L sanctioned
₹11.72 L spent (93%)
08
Land Development
5 works
₹9.86 L sanctioned
₹17.22 L spent (175%)
09
Constr of Cement Concrete Roads
12 works
₹8.38 L sanctioned
₹9.47 L spent (113%)
10
Construction of Crematorium
3 works
₹5.20 L sanctioned
₹4.99 L spent (96%)