MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
35,057
Sanctioned (pure scheme)
₹460.29 Cr
Expenditure since inception
₹295.73 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
1,701 works
₹101.40 Cr sanctioned
₹67.99 Cr spent (67%)
02
Plantation
1,294 works
₹48.85 Cr sanctioned
₹18.60 Cr spent (38%)
03
Construction of Check Dam/Stop Dam
1,579 works
₹45.07 Cr sanctioned
₹28.21 Cr spent (63%)
04
Land Development
5,790 works
₹35.66 Cr sanctioned
₹15.76 Cr spent (44%)
05
Construction of Bund
1,398 works
₹34.57 Cr sanctioned
₹15.75 Cr spent (46%)
06
Construction of Trench
978 works
₹32.73 Cr sanctioned
₹26.31 Cr spent (80%)
07
Rural Housing
15,686 works
₹30.07 Cr sanctioned
₹28.54 Cr spent (95%)
08
Construction of Percolation Tank
385 works
₹19.93 Cr sanctioned
₹15.24 Cr spent (76%)
09
Constr of Cement Concrete Roads
845 works
₹17.08 Cr sanctioned
₹10.12 Cr spent (59%)
10
Construction of Well
578 works
₹12.03 Cr sanctioned
₹7.70 Cr spent (64%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 15,686 30.07 28.54
95%
2 Land Development 5,790 35.66 15.76
44%
3 Construction of Road and Culvert 1,701 101.40 67.99
67%
4 Construction of Check Dam/Stop Dam 1,579 45.07 28.21
63%
5 Construction of Toilets 1,409 1.07 0.67
63%
6 Construction of Bund 1,398 34.57 15.75
46%
7 Plantation 1,294 48.85 18.60
38%
8 Construction of Trench 978 32.73 26.31
80%
9 Constr of Cement Concrete Roads 845 17.08 10.12
59%
10 Farm Pond 775 9.76 7.36
75%
11 Construction of Well 578 12.03 7.70
64%
12 Construction of Percolation Tank 385 19.93 15.24
76%
13 Well Recharge 244 3.07 1.58
52%
14 Construction of Recharge Pits 240 1.21 0.84
70%
15 Construction of Crematorium 239 8.59 5.56
65%
16 Culvert 202 8.68 6.88
79%
17 Repair & maint of Pond/ Tank 159 5.81 4.42
76%
18 Construction of NADEP/Vermi Compost Pit 132 0.48 0.24
51%
19 Solid and Liquid Waste Management 129 0.35 0.17
48%
20 Construction of Play field 125 5.38 3.74
70%
21 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 121 3.97 3.12
78%
22 Renovation of traditional water bodies 94 3.19 2.61
82%
23 Boulder Check/Gully Plug 90 2.15 1.54
72%
24 Construction of Tank 80 3.92 3.00
77%
25 Cattle Shed 77 1.32 0.91
69%
26 Repair & maint of Percolation Tank 75 3.81 3.05
80%
27 Roof Water Harvesting on gov/panchayat bldg 65 1.15 0.88
76%
28 Repair & Maint of Check Dam/Stop Dam 54 2.57 1.96
77%
29 Terracing 54 1.76 1.41
80%
30 Community Sanitary Complex 52 0.26 0.19
74%
31 Repair & maint of Water Harvesting Structures 50 1.87 1.55
83%
32 Constr of Aganwadi 37 0.67 0.50
75%
33 Constr of GP Bhawan 36 1.72 1.33
77%
34 Construction of Canal 30 1.92 1.47
77%
35 Repair & Maint of Canal 30 1.22 1.03
84%
36 Constr of Gabion 26 0.60 0.43
72%
37 Repair & Maint of Bund 24 1.01 0.83
83%
38 Underground Dyke for Ground Water Recharge 20 0.63 0.43
68%
39 Renovation of Canal 18 0.62 0.53
85%
40 Construction of Spur 13 0.54 0.45
84%
41 Other Works 12 0.10 0.05
52%
42 Constr of Compound wall 11 0.17 0.13
76%
43 Repair & maint of Road 11 0.72 0.61
86%
44 Repair & Maint of Community infrastructure 10 0.23 0.19
83%
45 Constr of Food Grain storage 9 0.46 0.34
73%
46 Goat Shelter 9 0.08 0.06
77%
47 Works for Flood Control and Protection 9 0.36 0.31
86%
48 Construction of Embankment 8 0.38 0.30
80%
49 Constr of Kitchen Shed 7 0.03 0.02
73%
50 Construction of building/workshed for SHG 5 0.18 0.15
84%
51 Nursery Development 5 0.16 0.12
71%
52 Lining of Canal 5 0.26 0.19
73%
53 Construction of Village Haats 5 0.13 0.13
98%
54 Grass Land Development 5 0.18 0.11
58%
55 Poultry Shelter 3 0.02 0.02
95%
56 Repaire and Maint of NADEP/Vermi Compost Pit 3 0.00 0.00
85%
57 Bio-Fertilizer 2 0.05 0.04
91%
58 Bio-gas plant 1 0.01 0.00
48%
59 Water Converation - Others 1 0.02 0.00
12%
60 Deepening / Desilting of Flood Channels 1 0.01 0.01
78%
61 Strengthening of Embankment 1 0.05 0.04
84%
Total 35,057 460.29 295.73
All 61 rows (zero-value rows hidden) ⇩ Export to Excel