Showcase — Completed Works
Rollup last refreshed: 2026-08-25 08:55:11.826995
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
301 works
₹54.35 L sanctioned
₹53.06 L spent (98%)
02
Construction of Bund
108 works
₹49.73 L sanctioned
₹38.86 L spent (78%)
03
Farm Pond
58 works
₹47.92 L sanctioned
₹40.59 L spent (85%)
04
Construction of Check Dam/Stop Dam
34 works
₹32.29 L sanctioned
₹28.48 L spent (88%)
05
Construction of Trench
5 works
₹27.56 L sanctioned
₹18.06 L spent (66%)
06
Construction of Percolation Tank
3 works
₹26.44 L sanctioned
₹19.15 L spent (72%)
07
Constr of Cement Concrete Roads
14 works
₹18.69 L sanctioned
₹9.67 L spent (52%)
08
Construction of Tank
3 works
₹16.16 L sanctioned
₹10.77 L spent (67%)
09
Plantation
22 works
₹15.50 L sanctioned
₹6.94 L spent (45%)
10
Construction of Road and Culvert
9 works
₹11.80 L sanctioned
₹26.50 L spent (225%)