Showcase — Completed Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Land Development
129 works
₹80.69 L sanctioned
₹80.72 L spent (100%)
02
Construction of Road and Culvert
7 works
₹79.91 L sanctioned
₹68.93 L spent (86%)
03
Construction of Check Dam/Stop Dam
35 works
₹69.29 L sanctioned
₹76.09 L spent (110%)
04
Construction of Bund
31 works
₹54.19 L sanctioned
₹49.23 L spent (91%)
05
Constr of Cement Concrete Roads
12 works
₹34.42 L sanctioned
₹23.46 L spent (68%)
06
Plantation
4 works
₹16.76 L sanctioned
₹6.70 L spent (40%)
07
Construction of Percolation Tank
3 works
₹16.28 L sanctioned
₹13.04 L spent (80%)
08
Construction of Toilets
141 works
₹15.76 L sanctioned
₹15.07 L spent (96%)
09
Culvert
1 works
₹10.00 L sanctioned
₹9.74 L spent (97%)
10
Construction of Fish Drying Infrastructure
2 works
₹9.96 L sanctioned
₹8.34 L spent (84%)