Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
3,893 works
₹121.19 Cr sanctioned
₹115.81 Cr spent (96%)
02
Farm Pond
2,447 works
₹52.81 Cr sanctioned
₹49.12 Cr spent (93%)
03
Land Development
9,113 works
₹50.26 Cr sanctioned
₹51.41 Cr spent (102%)
04
Construction of Road and Culvert
720 works
₹40.68 Cr sanctioned
₹41.56 Cr spent (102%)
05
Construction of Bund
1,743 works
₹39.24 Cr sanctioned
₹32.53 Cr spent (83%)
06
Rural Housing
16,454 works
₹31.35 Cr sanctioned
₹30.03 Cr spent (96%)
07
Plantation
1,159 works
₹28.75 Cr sanctioned
₹16.44 Cr spent (57%)
08
Construction of Well
987 works
₹25.04 Cr sanctioned
₹15.11 Cr spent (60%)
09
Repair & maint of Pond/ Tank
283 works
₹22.60 Cr sanctioned
₹18.68 Cr spent (83%)
10
Constr of Cement Concrete Roads
894 works
₹16.89 Cr sanctioned
₹11.84 Cr spent (70%)