Showcase — Completed Works
Rollup last refreshed: 2026-08-19 08:32:20.978731
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
23 works
₹1.95 Cr sanctioned
₹1.91 Cr spent (98%)
02
Construction of Bund
14 works
₹1.33 Cr sanctioned
₹1.32 Cr spent (99%)
03
Plantation
22 works
₹99.42 L sanctioned
₹86.67 L spent (87%)
04
Construction of Road and Culvert
17 works
₹81.32 L sanctioned
₹1.06 Cr spent (130%)
05
Construction of Trench
7 works
₹54.44 L sanctioned
₹52.25 L spent (96%)
06
Rural Housing
259 works
₹46.22 L sanctioned
₹47.35 L spent (102%)
07
Boulder Check/Gully Plug
3 works
₹28.03 L sanctioned
₹27.91 L spent (100%)
08
Land Development
40 works
₹27.49 L sanctioned
₹34.26 L spent (125%)
09
Cattle Shed
29 works
₹27.41 L sanctioned
₹25.00 L spent (91%)
10
Construction of Spur
2 works
₹24.97 L sanctioned
₹24.93 L spent (100%)