Showcase — Completed Works
Rollup last refreshed: 2026-08-26 17:54:53.293656
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
7 works
₹1.10 Cr sanctioned
₹92.53 L spent (84%)
02
Works for Flood Control and Protection
3 works
₹30.99 L sanctioned
₹24.89 L spent (80%)
03
Plantation
7 works
₹20.99 L sanctioned
₹4.42 L spent (21%)
04
Construction of Well
9 works
₹15.87 L sanctioned
₹15.77 L spent (99%)
05
Rural Housing
71 works
₹11.52 L sanctioned
₹11.39 L spent (99%)
06
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹7.70 L sanctioned
₹7.49 L spent (97%)
07
Constr of Cement Concrete Roads
8 works
₹6.90 L sanctioned
₹6.93 L spent (101%)
08
Renovation of traditional water bodies
3 works
₹6.50 L sanctioned
₹4.89 L spent (75%)
09
Construction of Check Dam/Stop Dam
1 works
₹5.36 L sanctioned
₹5.11 L spent (95%)
10
Constr of Aganwadi
2 works
₹3.60 L sanctioned
₹3.62 L spent (101%)