Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
291 works
₹37.43 Cr sanctioned
₹32.78 Cr spent (88%)
02
Construction of Well
1,114 works
₹20.93 Cr sanctioned
₹18.24 Cr spent (87%)
03
Plantation
725 works
₹18.10 Cr sanctioned
₹5.38 Cr spent (30%)
04
Rural Housing
8,911 works
₹15.79 Cr sanctioned
₹15.46 Cr spent (98%)
05
Works for Flood Control and Protection
125 works
₹11.18 Cr sanctioned
₹9.13 Cr spent (82%)
06
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
91 works
₹7.09 Cr sanctioned
₹5.84 Cr spent (82%)
07
Constr of Cement Concrete Roads
553 works
₹6.89 Cr sanctioned
₹5.60 Cr spent (81%)
08
Repair & maint of Pond/ Tank
101 works
₹5.46 Cr sanctioned
₹4.60 Cr spent (84%)
09
Construction of Check Dam/Stop Dam
108 works
₹4.68 Cr sanctioned
₹3.87 Cr spent (83%)
10
Construction of Percolation Tank
52 works
₹3.54 Cr sanctioned
₹2.93 Cr spent (83%)